This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 02221 BUILDING DEMOLITION
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolishing designated structures.
2. Demolishing designated foundations.
3. Demolishing designated slabs-on-grade.
4. Disconnecting and capping designated utilities.
5. Filling designated underground tanks.
6. Removing designated items for reuse and Owner’s retention.
7. Protecting items designated to remain.
8. Removing demolished materials.
1.2 SUBMITTALS
A. Demolition Schedule: Indicate overall schedule, description of demolition removal procedures and interruptions required for utility and building services for review and approval by Owner.
B. Shop Drawings:
1. Submit under provisions of Section 01330 – Submittal Procedures.
2. Indicate location and construction of temporary work.
1.3 CLOSEOUT SUBMITTALS
A. Section 01700 - Execution Requirements: Requirements for submittals.
B. Project Record Documents: Accurately record actual locations of capped utilities, concealed utilities discovered during demolition, subsurface obstructions, and limits of buried structure removal.
1.4 QUALITY ASSURANCE
A. Conform to applicable code for demolition work, safety of adjacent structures, dust control, products requiring electrical disconnection and re-connection, and disposal of demolition wastes.
B. Conform to applicable code for procedures when hazardous or contaminated materials are discovered.
C. Obtain required permits from authorities having jurisdiction.
A.
1.5 SEQUENCING
A. Section 01100 - Summary of Work: Requirements for sequencing.
B. All asbestos removal activities must be completed prior to commencing demolition work.
1.6 SCHEDULING
A. Section 01323 - Network Analysis Schedules: Requirements for scheduling.
B. Schedule Work to precede site excavation work and new construction.
C. Cooperate with Owner in scheduling noisy operations and waste removal that may impact Owners operation and adjoining property owners.
D. Coordination:
1. Perform demolition work in a manner which does not interfere with the Owner’s operations.
2. Coordinate demolition work so that new construction may proceed without undue delay.
1.7 ASBESTOS REMOVAL
A. Provide personnel certified to conduct and supervise asbestos removal activities.
B. Comply with federal and state regulations covering the removal and disposal of asbestos- containing materials.
C. See Asbestos Building Inspection reports for the site attached to this section. Asbestos- containing materials were found only in the floor tile in Bldg 15 Battery A Control Building, described as Category I non-friable. See attached testing reports.
PART 2 PRODUCTS
2.1 FILL MATERIALS
A. Fill Material: Specified in Section 02320.
PART 3 EXECUTION
3.1 EXAMINATION
A. Make arrangements with building owners and occupants to survey interior and exterior of existing buildings.
B. Survey and record condition of existing facilities to remain in-place that may be affected by the demolition work. After work is completed, restore facilities to original condition at no additional cost to the Owner.
A.
3.2 PREPARATION
A. Obtain written release from Owner before beginning demolition for each structure.
B. Notify affected utility companies before starting work to permit them to disconnect, remove, or relocate services at existing facilities. Comply with their requirements.
C. Reroute or shut off electrical, HVAC, process, and plumbing services outside the area of demolition.
D. Mark location and termination of utilities.
E. Salvage items specified for reuse in the Work or specified to be delivered to the Owner.
F. Erect and maintain temporary barriers and security devices around perimeter of demolition site, including warning signs and lights, and similar measures, for protection of the public, Owner, and existing improvements indicated to remain.
G. Drain or pump out basins to be demolished or abandoned. Dispose of liquid wastes properly.
H. Erect and maintain temporary partitions to prevent spread of dust, odors, and noise to permit continued Owner occupancy.
I. Schedule completion of asbestos removal prior to demolition.
3.3 DEMOLITION REQUIREMENTS
A. Use of explosives is not permitted without prior approval by Owner.
B. Conduct demolition to minimize interference with adjacent structures and plant operations.
C. Do not close or obstruct roadways, sidewalks, or hydrants without permits.
D. Provide appropriate temporary signage including signage for exit or building egress.
E. Do not close or obstruct building egress path.
F. Protection:
1. Structural stability of structures adjacent to or affected by demolition work shall be the Contractor’s responsibility.
2. Prevent movement or settlement of adjacent structures. Provide bracing and shoring as required.
3. Maintain in service and protect from damage existing facilities, utilities, and equipment to remain.
4. Existing landscaping materials, trees, appurtenances, structures, and utilities indicated to remain.
5. Erect and maintain weatherproof closures for exterior openings.
1.
G. Cease operations immediately when adjacent structures appear to be in danger. Notify Architect/Engineer. Do not resume operations until directed.
H. Conduct operations with minimum interference to public or private accesses. Maintain egress and access at all times.
I. Obtain written permission from adjacent property owners when demolition equipment will traverse, infringe upon, or limit access to their property.
J. Sprinkle Work with water to minimize dust. Provide hoses and water connections required for this purpose.
3.4 DEMOLITION
A. Conduct demolition work as shown on the Drawings.
B. Disconnect, remove and cap designated utilities within demolition areas. Remove utilities and piping to limits shown on the Drawings. Plug or seal permanently with steel cap, concrete plug, or other approved method. Remove abandoned utilities and underground piping within influence zone of proposed piping and structures.
C. Remove foundation walls and footings to minimum of two feet below finished grade within area of new construction unless shown otherwise on the Drawings.
D. Remove concrete slabs-on-grade.
E. Empty underground tanks located within demolition area.
F. Fill underground tanks with fill material as specified in Section 02320. Disconnect and remove piping.
G. Carefully remove building components indicated to be reused.
1. Disassemble components as required to permit removal.
2. Package small and loose parts to avoid loss.
3. Mark components and packaged parts to permit reinstallation.
4. Store components, protected from construction operations, until reinstalled.
H. Backfill areas excavated, open pits, and holes resulting from demolition, in accordance with Section 02320.
I. Rough grade and compact areas affected by demolition to maintain site grades and contours as shown on the Drawings.
J. Continuously clean up and remove demolished materials from site. Do not allow materials to accumulate on site.
K. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.
L. Remove temporary Work.
A.
3.5 SALVAGE
A. Salvage materials indicated on the Drawings.
B. Owner has first right to building components, piping, valves, wire and equipment being removed.
1. Coordinate with Owner to identify items to be removed and delivered to Owner
C. Tag components and equipment Owner designates for salvage.
D. Protect designated salvage items from demolition operations until items can be removed.
E. Package small and loose parts to avoid loss.
F. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item.
G. Remove and dispose of all piping, valves and equipment from site not required by Owner.
3.6 DISPOSAL
A. All waste materials from demolition work shall be removed from the site and disposed of in accordance with all applicable laws and regulations.
END OF SECTION
Water and Wastewater Specifications
Catalog of specifications describing water and waste water equipment.
Saturday, January 31, 2015
SECTION 01730 OPERATION AND MAINTENANCE MANUALS
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01730
OPERATION AND MAINTENANCE MANUALS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Format and content of manuals.
B. Equipment data form.
C. Operation and maintenance manual submittal checklist.
1.2 QUALITY ASSURANCE
A. Prepare instructions and data by personnel experienced in maintenance and operation of described products.
1.3 FORMAT
A. Prepare data in the form of an instructional manual.
B. Binders: Commercial quality, 8-1/2 x 11 inch three-ring binders with hardback, cleanable, plastic covers; two inch maximum ring size. When multiple binders are used, correlate data into related consistent groupings.
C. Cover: Identify each binder on the cover and spine with typed or printed title OPERATION AND MAINTENANCE MANUAL; list title of Project and subject matter of contents.
D. Provide a Cover Page that provides the following information:
1. Title of project.
2. Specification number and title.
3. Manufacturer.
4. General Contractor.
5. Subcontractor.
6. Supplier.
E. Arrange content by systems under section numbers and sequence of Table of Contents of this Project Manual.
F. Provide tabbed flyleaf for each separate product and system, with typed description of product and major component parts of equipment. All tabs shall be legible with permanent smudge resistant lettering.
A.
G. Text: Manufacturer's printed data, or typewritten data on 20 pound paper. Manufacturer's printed data must be originals or copies of good quality and clearly legible. Fax copies of material are not acceptable and will be rejected.
H. Drawings 11 X 17 inch or smaller: Provide with reinforced punched binder tab. Bind in with text; fold 11 x 17 inch drawings to size of text pages.
I. Drawings larger than 11 X 17 inch: Provide clear plastic holder the size of the test pages, punched and bound in binder with the enclosed folded drawing.
1.4 CONTENTS, EACH VOLUME
A. Table of Contents: Provide title of Project; names, addresses, and telephone numbers of Engineer, and Contractor with name of responsible parties; schedule of products and systems, indexed to content of the volume.
B. For Each Product or System: List names, addresses and telephone numbers of Subcontractors and suppliers, including local source of supplies and replacement parts.
C. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information. Clearly mark the selected product by use of arrows, underlines, or circles where more than one product is shown. Use of highlighters to identify the selected product is unacceptable.
D. Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams.
E. Type Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions specified in Section 01400.
1.5 MANUAL FOR MATERIALS AND FINISHES
A. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Provide information for re-ordering custom manufactured products.
B. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
C. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.
D. Additional Requirements: As specified in individual product specification Sections.
E. Provide a listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.
A.
1.6 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, complete nomenclature and commercial number of replaceable parts, complete nameplate data, and P&ID numbers as set forth in the Drawings.
B. Panelboard Circuit Directories: Provide electrical service characteristics, controls and communications.
C. Include color-coded wiring diagrams as installed.
D. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and any special operating instructions.
E. Maintenance Requirements: Include routine procedures and guide for trouble-shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.
F. Provide servicing and lubrication schedule, and list of lubricants required.
G. Include manufacturer's printed operation and maintenance instructions.
H. Include sequence of operation by controls manufacturer.
I. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.
J. Provide control diagrams by controls manufacturer as installed. These shall be ladder diagrams, instrument loop diagrams, and electrical schematics as appropriate.
K. Provide Contractor's coordination drawings, with color-coded piping diagrams as installed.
L. Provide charts of valve tag numbers, with location and function of each valve, keyed to P&ID numbers as set forth in the Drawings.
M. Provide list of original manufacturer's spare parts, predicted life, current prices, and recommended quantities to be maintained in storage.
N. Bill of material.
O. Completed typewritten equipment data form included with this section. Manufacturer's standard form will not be acceptable.
P. Manufacturer's safety instructions.
Q. Include test and balancing reports as specified in Division 15.
A.
R. Additional Requirements: As specified in individual product specification Sections.
S. Provide a listing in Table of Contents for design data, with tabbed flysheet and space for insertion of data.
1.7 SUBMITTALS
A. Submit four copies for review within 60 days after time Contractor receives approved Shop Drawings for equipment/systems from Engineer.
B. Progress payments for equipment delivered, stored, or installed under these Contract Documents will not be made beyond 50% of the scheduled value until copies of the O&M data are delivered to and approved by Engineer. Progress payments for control systems packaged with equipment will not be made beyond 50% of the scheduled value until O&M data revisions are incorporated into equipment and control system manuals delivered and approved by Engineer.
C. Operation and maintenance manual submittals shall be accompanied by the checklist attached to this section indicating that the requirements of this section have been met in its entirety. Engineer will reject submittals without completed checklist. Pages for all submittals shall be numbered.
D. Engineer's review and acceptance of operation and maintenance manuals will be only for conformance with requirements of this section, for form of submittal and organization of data and completeness of information provided, but not for technical content or coordination between individual suppliers of equipment or system(s).
E. Provide four hard copies of the final approved O&M manuals and one electronic version as described herein.
F. Contractor is responsible for producing an electronic version of the Equipment Operations and Maintenance (O&M) Manuals Manual. The Electronic Equipment O&M Manual shall be delivered in Portable Document Format (PDF). The entire manual may be converted to PDF via scanning or other method of conversion. Drawings or other graphics must be converted to PDF format and made part of the PDF document. The Contractor shall provide all Equipment O&M Manuals in the electronic format as described herein.
G. The filename for the Equipment O&M Manual submittal will be provided with the request for final Equipment O&M Manuals. Filenames use the "eight dot three" convention (XXXXX_YY.PDF) where XXXXX is the specification section number and YY is an ID number. No one file shall be larger than 10 MB. If technical problems require that the submittal be divided into more than one file, a letter extension shall be added to the end of each filename. (Example: 19876_01a.pdf).
H. The number of files shall be kept to a minimum. Equipment O&M Manuals that span more than one file shall have the final Bookmark "Return to Table of Contents" which shall take the User to the first file on the Equipment O&M Manual.
A.
I. All text (word processed), spreadsheets, and electronic graphics shall be delivered in portable document form (*.PDF). The resolution of all scanned images shall be a minimum of 300 dpi unless otherwise requested by Engineer. Scanned images shall be processed with the "original image with hidden text" option (Adobe Acrobat 8 or higher). This results in a clear image and provides for optical character recognition (OCR) and word search functionality. Graphical files shall be fully searchable. All submittals must be indexed with the Adobe Catalog feature. Placement and structure of index files shall be in accordance with Adobe's recommendations to minimize problems when transferring files. Successful searches for words or strings in the PDF document shall demonstrate proof of OCR.
J. Rotate pages viewed in landscape to the appropriate position for easy reading on a computer monitor.
K. Bookmarks shall be created in the navigation frame for each entry in the Table of Contents. Three levels deep is usually enough (i.e., "Chapter", "Section", "Subsection"); however, complex submittals like instrumentation and electrical may be required at the discretion of Engineer. When setting bookmarks for Chapter level heading, the page shall be displayed at Full Page. Section and Subsection level heading pages shall be displayed as a magnified view. Bookmarks shall be displayed as subordinate to other bookmarks in their hierarchy set so that only the Chapter level headings are displayed.
L. Thumbnails shall be generated and embedded in each PDF file.
M. Files shall be delivered without Security features activated. Password protected files will be unacceptable.
N. The opening view for PDF files shall be set as follows:
1.
Initial View:
Bookmarks and Page
2.
Magnification:
Fit In Window
3.
Page Layout:
Single Page
O. The file shall open to the cover page of the Equipment O&M Manual with bookmarks to the left. The first bookmark shall be the name of Equipment O&M Manual.
P. The submittal shall be delivered on CD after all Equipment O&M Manuals have been received and approved. Each CD shall be labeled, at a minimum, as follows, including:
1) CD-ROM disks, 2) jewel cases, and 3) hard copies.
1. Manufacturer name, point of contact, telephone number, facsimile number, and e-mail address as appropriate
2. Equipment name and/or O&M title spelled out in complete words
a. Example “Operations and Maintenance Manual - Horizontal Centrifugal Nonclog Pumps”
3. Specifications section number
4. Project name
5. Date and File Name: Example "12-20-15", "19876_01.pdf"
Q. Contractor shall reprocess any portion of the document that does not view or print to Owner's satisfaction.
A.
R. Contractor shall obtain all copyright permissions associated with conversion of O&M manual information into electronic format.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
EQUIPMENT DATA FORM (Page 1 of 3)
PROJECT NAME CONTRACT NO. CONTRACTOR
EQUIPMENT NO. DESCRIPTION LOCATION
MANUFACTURER PURCHASED FROM PURCHASE DATE VENDOR ORDER NO. PURCHASE PRICE
LOCAL SUPPLIER PHONE ADDRESS MODEL NO. SHIPPING WT/UNIT NO. OF UNITS SERIAL NOS.
NAMEPLATE DATA
ELECTRIC MOTOR PUMP/HVAC UNIT DRIVE/REDUCER OTHER (I&C)
MANUFACTURER: MANUFACTURER: MANUFACTURER: MANUFACTURER:
TYPE: []AC []DC TYPE
TYPE: []GEAR TYPE []V-BELT
HP RPM
SIZE CAPACITY_
[]CHAIN SIZE []VARIDRIVE
CAPACITY
SERVICE
VOLTAGE
PRESSURE_
FACTOR
RANGE
AMPERAGE
ROTATION
RATIO
PHASE
IMPELLER: SIZE
FRAME
MATERIAL
EQUIPMENT DATA FORM (Page 2 of 3)
MAINTENANCE SUMMARY
EQUIPMENT NO.
DESCRIPTION
MAINTENANCE OPERATION FREQUENCY
List briefly each maintenance operation List required frequency
required and refer to specific information of each maintenance
in Manufacturer's Maintenance Manual, if operation. applicable. Refer by symbol to "Lubricant
List" for Lubrication Operation.
EQUIPMENT DATA FORM (Page 3 of 3)
LUBRICANT/RECOMMENDED SPARE PARTS LIST
EQUIPMENT NO.
DESCRIPTION
LUBRICANT LIST
LUBRICANT
LUBRICANT TYPE RECOMMENDED
REFERENCE SYMBOL (MILITARY STANDARD) AND MANUFACTURER
List symbol in List general lubricant type List specific lubricant name, "maintenance operation” viscosity and manufacturer
RECOMMENDED SPARE PARTS LIST
UNIT
PART NO. DESCRIPTION UNIT QUANTITY COST
NOTE: Identify parts provided by this Contract with two asterisks. ADDITIONAL DATA AND REMARKS
O&M MANUAL SUBMITTAL CHECKLIST (Page 1 of 5)
PROJECT NAME
CONTRACT NO.
CONTRACTOR
EQUIPMENT/SYSTEM
SECTION NO.
MANUFACTURER/VENDOR
FORMAT
Size: 8-1/2 x 11 or 11 x 17
Paper: 20-pound minimum
Text: Printed data/neatly typed
Drawings: Standard size bound in text; in text-size labeled envelopes Tabbed Section Dividers
Cover Label: Title
Project Name Building/Structure ID Equipment Name Specification Section
Binders: Plastic Cover
O&M MANUAL SUBMITTAL CHECKLIST (Page 2 of 5)
GENERAL CONTENTS
Not
Page
Provided
Applicable
No.
One Specification Only Title Page:
Title Project title
Building/structure ID Equipment name Specification section number Contractor ID
Subcontractor ID Purchase order data Manufacturer ID Service/parts supplier ID Product List
Table of Contents Tabbed Sections: Pertinent data sheets Annotated as needed Text:
Pertinent to project Annotated Drawings:
Illustrate product and components Control and flow diagrams Special Information: Interrelationships of equipment and components
Instructions and procedures Instructions organized in Instructions in logical Glossary
Warranty, Bond, Service Contract
O&M MANUAL SUBMITTAL CHECKLIST (Page 3 of 5)
MANUAL FOR MATERIALS AND FINISHES
Not Page
Provided Applicable No.
Building Products: Product data Catalog number Size
Composition
Color and texture designations Care and Maintenance Instructions Recommended cleaning agents and methods
Cleaning precautions
Cleaning and maintenance schedule Moisture Protection Products: Product data listing
Chemical composition Installation details Inspection recommendations Maintenance and repair Additional Data as Required
O&M MANUAL SUBMITTAL CHECKLIST (Page 4 of 5)
MANUAL FOR EQUIPMENT AND SYSTEMS
Not Page
Provided Applicable No.
Description of Unit and Components: Equipment functions
Normal operating characteristics Limiting conditions Performance curves Engineering data
Test data
Replaceable parts list (with numbers) P&ID numbers
Operating Procedures: Startup
Break-in
Routine/normal operation Regulation and control Stopping and shutdown Emergency
Seasonal operation Special instructions Maintenance Procedures:
Routine/normal instructions Troubleshooting guide Disassembly/reassembly/repair Alignment/adjusting/balancing Servicing and Lubrication: List of lubricants
Lubrication schedule Maintenance schedule Safety Precautions/Features
Sequence of Operation of Controls Assembly Drawings
Parts List and Illustrations: Predicted life
Recommended spare parts list and prices Control Diagrams/Schematics
Bill of Materials
O&M MANUAL SUBMITTAL CHECKLIST (Page 5 of 5)
Not Page
Provided Applicable No.
Completed Equipment Data Form per Specification
Valves
Catalog Cuts and Tag Numbers Maintenance Instructions Panelboard Directories: Electrical
Controls Communications Instrumentation Loops: Diagrams
Components list each circuit/loop Additional Data As Required
SECTION 01730
OPERATION AND MAINTENANCE MANUALS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Format and content of manuals.
B. Equipment data form.
C. Operation and maintenance manual submittal checklist.
1.2 QUALITY ASSURANCE
A. Prepare instructions and data by personnel experienced in maintenance and operation of described products.
1.3 FORMAT
A. Prepare data in the form of an instructional manual.
B. Binders: Commercial quality, 8-1/2 x 11 inch three-ring binders with hardback, cleanable, plastic covers; two inch maximum ring size. When multiple binders are used, correlate data into related consistent groupings.
C. Cover: Identify each binder on the cover and spine with typed or printed title OPERATION AND MAINTENANCE MANUAL; list title of Project and subject matter of contents.
D. Provide a Cover Page that provides the following information:
1. Title of project.
2. Specification number and title.
3. Manufacturer.
4. General Contractor.
5. Subcontractor.
6. Supplier.
E. Arrange content by systems under section numbers and sequence of Table of Contents of this Project Manual.
F. Provide tabbed flyleaf for each separate product and system, with typed description of product and major component parts of equipment. All tabs shall be legible with permanent smudge resistant lettering.
A.
G. Text: Manufacturer's printed data, or typewritten data on 20 pound paper. Manufacturer's printed data must be originals or copies of good quality and clearly legible. Fax copies of material are not acceptable and will be rejected.
H. Drawings 11 X 17 inch or smaller: Provide with reinforced punched binder tab. Bind in with text; fold 11 x 17 inch drawings to size of text pages.
I. Drawings larger than 11 X 17 inch: Provide clear plastic holder the size of the test pages, punched and bound in binder with the enclosed folded drawing.
1.4 CONTENTS, EACH VOLUME
A. Table of Contents: Provide title of Project; names, addresses, and telephone numbers of Engineer, and Contractor with name of responsible parties; schedule of products and systems, indexed to content of the volume.
B. For Each Product or System: List names, addresses and telephone numbers of Subcontractors and suppliers, including local source of supplies and replacement parts.
C. Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information. Clearly mark the selected product by use of arrows, underlines, or circles where more than one product is shown. Use of highlighters to identify the selected product is unacceptable.
D. Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams.
E. Type Text: As required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions specified in Section 01400.
1.5 MANUAL FOR MATERIALS AND FINISHES
A. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Provide information for re-ordering custom manufactured products.
B. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
C. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.
D. Additional Requirements: As specified in individual product specification Sections.
E. Provide a listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.
A.
1.6 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Each Item of Equipment and Each System: Include description of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineering data and tests, complete nomenclature and commercial number of replaceable parts, complete nameplate data, and P&ID numbers as set forth in the Drawings.
B. Panelboard Circuit Directories: Provide electrical service characteristics, controls and communications.
C. Include color-coded wiring diagrams as installed.
D. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and any special operating instructions.
E. Maintenance Requirements: Include routine procedures and guide for trouble-shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.
F. Provide servicing and lubrication schedule, and list of lubricants required.
G. Include manufacturer's printed operation and maintenance instructions.
H. Include sequence of operation by controls manufacturer.
I. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.
J. Provide control diagrams by controls manufacturer as installed. These shall be ladder diagrams, instrument loop diagrams, and electrical schematics as appropriate.
K. Provide Contractor's coordination drawings, with color-coded piping diagrams as installed.
L. Provide charts of valve tag numbers, with location and function of each valve, keyed to P&ID numbers as set forth in the Drawings.
M. Provide list of original manufacturer's spare parts, predicted life, current prices, and recommended quantities to be maintained in storage.
N. Bill of material.
O. Completed typewritten equipment data form included with this section. Manufacturer's standard form will not be acceptable.
P. Manufacturer's safety instructions.
Q. Include test and balancing reports as specified in Division 15.
A.
R. Additional Requirements: As specified in individual product specification Sections.
S. Provide a listing in Table of Contents for design data, with tabbed flysheet and space for insertion of data.
1.7 SUBMITTALS
A. Submit four copies for review within 60 days after time Contractor receives approved Shop Drawings for equipment/systems from Engineer.
B. Progress payments for equipment delivered, stored, or installed under these Contract Documents will not be made beyond 50% of the scheduled value until copies of the O&M data are delivered to and approved by Engineer. Progress payments for control systems packaged with equipment will not be made beyond 50% of the scheduled value until O&M data revisions are incorporated into equipment and control system manuals delivered and approved by Engineer.
C. Operation and maintenance manual submittals shall be accompanied by the checklist attached to this section indicating that the requirements of this section have been met in its entirety. Engineer will reject submittals without completed checklist. Pages for all submittals shall be numbered.
D. Engineer's review and acceptance of operation and maintenance manuals will be only for conformance with requirements of this section, for form of submittal and organization of data and completeness of information provided, but not for technical content or coordination between individual suppliers of equipment or system(s).
E. Provide four hard copies of the final approved O&M manuals and one electronic version as described herein.
F. Contractor is responsible for producing an electronic version of the Equipment Operations and Maintenance (O&M) Manuals Manual. The Electronic Equipment O&M Manual shall be delivered in Portable Document Format (PDF). The entire manual may be converted to PDF via scanning or other method of conversion. Drawings or other graphics must be converted to PDF format and made part of the PDF document. The Contractor shall provide all Equipment O&M Manuals in the electronic format as described herein.
G. The filename for the Equipment O&M Manual submittal will be provided with the request for final Equipment O&M Manuals. Filenames use the "eight dot three" convention (XXXXX_YY.PDF) where XXXXX is the specification section number and YY is an ID number. No one file shall be larger than 10 MB. If technical problems require that the submittal be divided into more than one file, a letter extension shall be added to the end of each filename. (Example: 19876_01a.pdf).
H. The number of files shall be kept to a minimum. Equipment O&M Manuals that span more than one file shall have the final Bookmark "Return to Table of Contents" which shall take the User to the first file on the Equipment O&M Manual.
A.
I. All text (word processed), spreadsheets, and electronic graphics shall be delivered in portable document form (*.PDF). The resolution of all scanned images shall be a minimum of 300 dpi unless otherwise requested by Engineer. Scanned images shall be processed with the "original image with hidden text" option (Adobe Acrobat 8 or higher). This results in a clear image and provides for optical character recognition (OCR) and word search functionality. Graphical files shall be fully searchable. All submittals must be indexed with the Adobe Catalog feature. Placement and structure of index files shall be in accordance with Adobe's recommendations to minimize problems when transferring files. Successful searches for words or strings in the PDF document shall demonstrate proof of OCR.
J. Rotate pages viewed in landscape to the appropriate position for easy reading on a computer monitor.
K. Bookmarks shall be created in the navigation frame for each entry in the Table of Contents. Three levels deep is usually enough (i.e., "Chapter", "Section", "Subsection"); however, complex submittals like instrumentation and electrical may be required at the discretion of Engineer. When setting bookmarks for Chapter level heading, the page shall be displayed at Full Page. Section and Subsection level heading pages shall be displayed as a magnified view. Bookmarks shall be displayed as subordinate to other bookmarks in their hierarchy set so that only the Chapter level headings are displayed.
L. Thumbnails shall be generated and embedded in each PDF file.
M. Files shall be delivered without Security features activated. Password protected files will be unacceptable.
N. The opening view for PDF files shall be set as follows:
1.
Initial View:
Bookmarks and Page
2.
Magnification:
Fit In Window
3.
Page Layout:
Single Page
O. The file shall open to the cover page of the Equipment O&M Manual with bookmarks to the left. The first bookmark shall be the name of Equipment O&M Manual.
P. The submittal shall be delivered on CD after all Equipment O&M Manuals have been received and approved. Each CD shall be labeled, at a minimum, as follows, including:
1) CD-ROM disks, 2) jewel cases, and 3) hard copies.
1. Manufacturer name, point of contact, telephone number, facsimile number, and e-mail address as appropriate
2. Equipment name and/or O&M title spelled out in complete words
a. Example “Operations and Maintenance Manual - Horizontal Centrifugal Nonclog Pumps”
3. Specifications section number
4. Project name
5. Date and File Name: Example "12-20-15", "19876_01.pdf"
Q. Contractor shall reprocess any portion of the document that does not view or print to Owner's satisfaction.
A.
R. Contractor shall obtain all copyright permissions associated with conversion of O&M manual information into electronic format.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
EQUIPMENT DATA FORM (Page 1 of 3)
PROJECT NAME CONTRACT NO. CONTRACTOR
EQUIPMENT NO. DESCRIPTION LOCATION
MANUFACTURER PURCHASED FROM PURCHASE DATE VENDOR ORDER NO. PURCHASE PRICE
LOCAL SUPPLIER PHONE ADDRESS MODEL NO. SHIPPING WT/UNIT NO. OF UNITS SERIAL NOS.
NAMEPLATE DATA
ELECTRIC MOTOR PUMP/HVAC UNIT DRIVE/REDUCER OTHER (I&C)
MANUFACTURER: MANUFACTURER: MANUFACTURER: MANUFACTURER:
TYPE: []AC []DC TYPE
TYPE: []GEAR TYPE []V-BELT
HP RPM
SIZE CAPACITY_
[]CHAIN SIZE []VARIDRIVE
CAPACITY
SERVICE
VOLTAGE
PRESSURE_
FACTOR
RANGE
AMPERAGE
ROTATION
RATIO
PHASE
IMPELLER: SIZE
FRAME
MATERIAL
EQUIPMENT DATA FORM (Page 2 of 3)
MAINTENANCE SUMMARY
EQUIPMENT NO.
DESCRIPTION
MAINTENANCE OPERATION FREQUENCY
List briefly each maintenance operation List required frequency
required and refer to specific information of each maintenance
in Manufacturer's Maintenance Manual, if operation. applicable. Refer by symbol to "Lubricant
List" for Lubrication Operation.
EQUIPMENT DATA FORM (Page 3 of 3)
LUBRICANT/RECOMMENDED SPARE PARTS LIST
EQUIPMENT NO.
DESCRIPTION
LUBRICANT LIST
LUBRICANT
LUBRICANT TYPE RECOMMENDED
REFERENCE SYMBOL (MILITARY STANDARD) AND MANUFACTURER
List symbol in List general lubricant type List specific lubricant name, "maintenance operation” viscosity and manufacturer
RECOMMENDED SPARE PARTS LIST
UNIT
PART NO. DESCRIPTION UNIT QUANTITY COST
NOTE: Identify parts provided by this Contract with two asterisks. ADDITIONAL DATA AND REMARKS
O&M MANUAL SUBMITTAL CHECKLIST (Page 1 of 5)
PROJECT NAME
CONTRACT NO.
CONTRACTOR
EQUIPMENT/SYSTEM
SECTION NO.
MANUFACTURER/VENDOR
FORMAT
Size: 8-1/2 x 11 or 11 x 17
Paper: 20-pound minimum
Text: Printed data/neatly typed
Drawings: Standard size bound in text; in text-size labeled envelopes Tabbed Section Dividers
Cover Label: Title
Project Name Building/Structure ID Equipment Name Specification Section
Binders: Plastic Cover
O&M MANUAL SUBMITTAL CHECKLIST (Page 2 of 5)
GENERAL CONTENTS
Not
Page
Provided
Applicable
No.
One Specification Only Title Page:
Title Project title
Building/structure ID Equipment name Specification section number Contractor ID
Subcontractor ID Purchase order data Manufacturer ID Service/parts supplier ID Product List
Table of Contents Tabbed Sections: Pertinent data sheets Annotated as needed Text:
Pertinent to project Annotated Drawings:
Illustrate product and components Control and flow diagrams Special Information: Interrelationships of equipment and components
Instructions and procedures Instructions organized in Instructions in logical Glossary
Warranty, Bond, Service Contract
O&M MANUAL SUBMITTAL CHECKLIST (Page 3 of 5)
MANUAL FOR MATERIALS AND FINISHES
Not Page
Provided Applicable No.
Building Products: Product data Catalog number Size
Composition
Color and texture designations Care and Maintenance Instructions Recommended cleaning agents and methods
Cleaning precautions
Cleaning and maintenance schedule Moisture Protection Products: Product data listing
Chemical composition Installation details Inspection recommendations Maintenance and repair Additional Data as Required
O&M MANUAL SUBMITTAL CHECKLIST (Page 4 of 5)
MANUAL FOR EQUIPMENT AND SYSTEMS
Not Page
Provided Applicable No.
Description of Unit and Components: Equipment functions
Normal operating characteristics Limiting conditions Performance curves Engineering data
Test data
Replaceable parts list (with numbers) P&ID numbers
Operating Procedures: Startup
Break-in
Routine/normal operation Regulation and control Stopping and shutdown Emergency
Seasonal operation Special instructions Maintenance Procedures:
Routine/normal instructions Troubleshooting guide Disassembly/reassembly/repair Alignment/adjusting/balancing Servicing and Lubrication: List of lubricants
Lubrication schedule Maintenance schedule Safety Precautions/Features
Sequence of Operation of Controls Assembly Drawings
Parts List and Illustrations: Predicted life
Recommended spare parts list and prices Control Diagrams/Schematics
Bill of Materials
O&M MANUAL SUBMITTAL CHECKLIST (Page 5 of 5)
Not Page
Provided Applicable No.
Completed Equipment Data Form per Specification
Valves
Catalog Cuts and Tag Numbers Maintenance Instructions Panelboard Directories: Electrical
Controls Communications Instrumentation Loops: Diagrams
Components list each circuit/loop Additional Data As Required
SECTION 01720 PROJECT RECORD DOCUMENTS
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01720 PROJECT RECORD DOCUMENTS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Maintenance of Documents and Samples.
B. Record Documents.
C. Submittals.
1.2 MAINTENANCE OF DOCUMENTS AND SAMPLES
A. Maintain at site, one copy of the following Record Documents:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change orders and other modifications to Contract.
5. Field orders, written instructions, or clarifications.
6. Approved submittals.
7. Field test records.
8. Construction photographs.
9. All associated permits.
10. Certificates of inspection and approvals.
B. Store documents and samples in Contractor's field office on-site apart from documents used for construction:
1. Provide files and racks for storage of documents.
2. Provide secure storage space for storage of samples.
C. Maintain documents in clean, dry, legible condition and in good order. Do not use record documents for construction purposes.
D. Make documents and samples available at all times for inspection by Engineer.
E. Failure to properly maintain record documents may be reason to delay a portion of progress payments until records comply with Contract Documents.
1.3 RECORD DOCUMENTS
A. Maintain record set of drawings and specifications legibly changed to transfer approved modifications in completed Work that differ from Contract Documents.
B. Label each document "Project Record" in neat, large printed letters.
A.
C. Record information concurrently with construction progress.
1. Do not conceal any work until required information is recorded.
2. Record changes made by Written Amendment, Field Order, Change Order, or Work Directive Change.
D. Specifications: Legibly mark and record at each section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and Modifications.
E. Drawings:
1. General:
a. All finished manhole rim and invert elevations, as well as sanitary and storm sewer invert elevations in structures and outfalls.
b. Depths of various elements of foundation in relation to finish first floor datum.
c. Horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
d. Location of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of structure.
e. Field changes.
f. Details not on original Drawings.
g. Location and identification of exposed interior piping.
2. Electrical:
a. Horizontal and vertical locations and size of underground cable, conduit, and duct runs dimensioned from established building lines.
b. Plan location and size of interior concealed and exposed feeders.
c. Size and location of access panels.
d. Departures from original drawings and electrical work revisions.
1.4 SUBMITTALS
A. At Substantial Completion:
1. Deliver one marked up set of Record Documents to Engineer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
SECTION 01720 PROJECT RECORD DOCUMENTS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Maintenance of Documents and Samples.
B. Record Documents.
C. Submittals.
1.2 MAINTENANCE OF DOCUMENTS AND SAMPLES
A. Maintain at site, one copy of the following Record Documents:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change orders and other modifications to Contract.
5. Field orders, written instructions, or clarifications.
6. Approved submittals.
7. Field test records.
8. Construction photographs.
9. All associated permits.
10. Certificates of inspection and approvals.
B. Store documents and samples in Contractor's field office on-site apart from documents used for construction:
1. Provide files and racks for storage of documents.
2. Provide secure storage space for storage of samples.
C. Maintain documents in clean, dry, legible condition and in good order. Do not use record documents for construction purposes.
D. Make documents and samples available at all times for inspection by Engineer.
E. Failure to properly maintain record documents may be reason to delay a portion of progress payments until records comply with Contract Documents.
1.3 RECORD DOCUMENTS
A. Maintain record set of drawings and specifications legibly changed to transfer approved modifications in completed Work that differ from Contract Documents.
B. Label each document "Project Record" in neat, large printed letters.
A.
C. Record information concurrently with construction progress.
1. Do not conceal any work until required information is recorded.
2. Record changes made by Written Amendment, Field Order, Change Order, or Work Directive Change.
D. Specifications: Legibly mark and record at each section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and Modifications.
E. Drawings:
1. General:
a. All finished manhole rim and invert elevations, as well as sanitary and storm sewer invert elevations in structures and outfalls.
b. Depths of various elements of foundation in relation to finish first floor datum.
c. Horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
d. Location of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of structure.
e. Field changes.
f. Details not on original Drawings.
g. Location and identification of exposed interior piping.
2. Electrical:
a. Horizontal and vertical locations and size of underground cable, conduit, and duct runs dimensioned from established building lines.
b. Plan location and size of interior concealed and exposed feeders.
c. Size and location of access panels.
d. Departures from original drawings and electrical work revisions.
1.4 SUBMITTALS
A. At Substantial Completion:
1. Deliver one marked up set of Record Documents to Engineer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
SECTION 01710 CLEANING
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01710 CLEANING
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Cleaning of existing tanks and facilities to be modified.
B. Cleaning during construction.
C. Dust control.
D. Final cleaning.
1.2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws.
1.3 SEQUENCING REQUIREMENTS
A. Sequencing of tank cleaning shall be as specified in Section 01100 SUMMARY OF WORK.
PART 2 PRODUCTS
2.1 MATERIALS
A. Use only those cleaning materials that will not create hazards to property or damage surfaces of material to be cleaned.
B. Water for Cleaning: Treated plant effluent (W3) is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) and / or non-potable water (W2) is available for use by the Contractor. Owner will pay costs of W1 and W2 water. Contractor shall provide temporary pumping and piping facilities to transport water as required.
PART 3 EXECUTION
3.1 CLEANING OF EXISTING TANKS AND FACILITIES TO BE MODIFIED
A. Contractor shall provide notice to Owner at least 20 days prior to the scheduled date for commencing cleaning operations. The Owner will pump out tank contents to a level of
2.0 feet of side-wall depth, then take the tank out of service and turn over to Contractor.
B. Contractor shall provide ventilation and means required to enter the tanks using existing roof access. The atmosphere in the digesters while in service and prior to ventilation can have low oxygen levels. The Contractor shall provide all safety equipment necessary to access the tanks and shall operate all ventilation equipment necessary to adequately protect the Contractor’s personnel. The Contractor shall provide all gas testing equipment, confined space entry equipment, communications, and trained personnel required to meet all OSHA and State of Illinois regulations.
C. Contractor shall provide a general wash to remove wastewater residues and solids from interior tank walls, ceilings and floors. Tank contents will include aerobic digested sludge, inorganic solids (sand, grit, gravel) and organic debris (hair, rags, stringy materials, plastics). Contractor shall provide means and methods suitable for removal of tank contents, including pumps, hoses, connection to water sources, power, and lighting.
D. The Contractor shall be responsible for removal, dewatering, and for the final disposition of the materials from the tanks in a landfill and in accordance with all local, state, and federal regulations. Disposal of residual solids in the plant will not be allowed. Contractor shall provide temporary means of dewatering residual solids from tank cleaning operations. Centrate or filtrate generated during dewatering may be disposed of to a plant drain, as approved by the Owner. The Owner reserves the right to disallow disposal of any waste stream that may negatively impact or impair plant operations.
E. Before any tank contents are removed from the treatment plant site, documentation shall be submitted demonstrating that the CONTRACTOR will comply with all regulations. Landfill manifests shall be provided as verification of disposal at a licensed landfill. The CONTRACTOR shall coordinate all hauling activities with the landfill.
F. Flush and drain all piping to be modified prior to construction. Contractor shall provide additional cleaning as required for proper construction.
G. Existing structures requiring cleaning prior to modifications include the following:
Structure name
Plan Dimensions (ft x ft)
Sidewall height above footing (ft)
Sidewall height above existing grade(1) (ft)
Volume of residuals (gallons) (2)
Aeration Tank No. 1
Pass No. 1
154 x 40
19
10 – 17
61,300
Pass No. 2
154 x 40
19
11 – 18
61,300
Pass No. 3
154 x 40
19
12 – 18
61,300
Aeration Tank No. 2
Pass No. 1
154 x 40
19
9 – 16
61,300
Pass No. 2
154 x 40
19
9 – 15
61,300
Pass No. 3
154 x 40
19
8 – 15
61,300
Aeration Tank No. 3
Pass No. 1
154 x 40
19
10 – 14
61,300
Pass No. 2
154 x 40
19
12 – 15
61,300
Pass No. 3
154 x 40
19
12 – 15
61,300
Aerobic Digester No. 1
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 2
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 3
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 4
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 5
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 6
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 7
72 x 40
19.5
11.5 – 14.5
27,000
Aerobic Digester No. 8
72 x 40
19.5
11.5 – 14.5
27,000
(1) Varies
(2) Volume of residuals to be removed calculated to the top of the existing diffuser elements.
3.2 CLEANING DURING CONSTRUCTION
A. Execute periodic cleaning to keep Work, site, and adjacent properties free from accumulations of waste materials, rubbish, and windblown debris resulting from construction operations.
B. Provide on-site containers for collection and removal of waste materials, debris, and rubbish in accordance with applicable regulations. Remove weekly and dispose of off- site.
C. Thoroughly clean all spilled dirt, gravel, or other foreign material caused by the construction operations from all streets and roads at the conclusion of each day's operation.
D. Provide daily cleaning of facilities in use by the Owner when construction dust, mud or debris interfere with the Owner’s operations.
E. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.
F. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.
3.3 DUST CONTROL
A. Clean interior space prior to start of finish painting and continue cleaning on as-needed basis until painting is completed.
B. Schedule operations so dust and other contaminants resulting from cleaning process will not fall on wet or newly coated surfaces.
C. Give all roads and haul roads used in the construction area an approved dust-preventive treatment and/or daily watering when requested by the Engineer to prevent dust. Applicable environmental regulations for dust prevention shall be strictly enforced.
3.4 FINAL CLEANING
A. Employ skilled workers for final cleaning.
A.
B. Execute final cleaning prior to final inspection.
C. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
D. Clean all interior walls, ceilings, floors, cabinets, and furniture.
E. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
F. Wash and shine glazing and mirrors.
G. Polish glossy surfaces to clear shine.
H. Ventilating Systems:
1. Clean permanent filters and replace disposable filters if units were operated during construction.
2. Clean ducts, blowers, and coils if units were operated without filters during construction.
I. Electrical Systems:
1. Leave electrical equipment rooms broom clean.
2. Clean interior of panel cabinets, pull boxes, and other equipment enclosures.
3. Wash and wipe clean lighting fixtures, lamps, and other electrical equipment that may have become soiled during installation.
4. Touch-up paint and repaint, if deterioration is extensive, electrical items delivered to job with finish coat of paint.
J. Clean debris from roofs, gutters, down spouts, and drainage systems.
K. Clean site; sweep paved areas, rake clean landscaped surfaces.
L. Remove waste and surplus materials, rubbish and construction from the site.
END OF SECTION
SECTION 01710 CLEANING
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Cleaning of existing tanks and facilities to be modified.
B. Cleaning during construction.
C. Dust control.
D. Final cleaning.
1.2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws.
1.3 SEQUENCING REQUIREMENTS
A. Sequencing of tank cleaning shall be as specified in Section 01100 SUMMARY OF WORK.
PART 2 PRODUCTS
2.1 MATERIALS
A. Use only those cleaning materials that will not create hazards to property or damage surfaces of material to be cleaned.
B. Water for Cleaning: Treated plant effluent (W3) is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) and / or non-potable water (W2) is available for use by the Contractor. Owner will pay costs of W1 and W2 water. Contractor shall provide temporary pumping and piping facilities to transport water as required.
PART 3 EXECUTION
3.1 CLEANING OF EXISTING TANKS AND FACILITIES TO BE MODIFIED
A. Contractor shall provide notice to Owner at least 20 days prior to the scheduled date for commencing cleaning operations. The Owner will pump out tank contents to a level of
2.0 feet of side-wall depth, then take the tank out of service and turn over to Contractor.
B. Contractor shall provide ventilation and means required to enter the tanks using existing roof access. The atmosphere in the digesters while in service and prior to ventilation can have low oxygen levels. The Contractor shall provide all safety equipment necessary to access the tanks and shall operate all ventilation equipment necessary to adequately protect the Contractor’s personnel. The Contractor shall provide all gas testing equipment, confined space entry equipment, communications, and trained personnel required to meet all OSHA and State of Illinois regulations.
C. Contractor shall provide a general wash to remove wastewater residues and solids from interior tank walls, ceilings and floors. Tank contents will include aerobic digested sludge, inorganic solids (sand, grit, gravel) and organic debris (hair, rags, stringy materials, plastics). Contractor shall provide means and methods suitable for removal of tank contents, including pumps, hoses, connection to water sources, power, and lighting.
D. The Contractor shall be responsible for removal, dewatering, and for the final disposition of the materials from the tanks in a landfill and in accordance with all local, state, and federal regulations. Disposal of residual solids in the plant will not be allowed. Contractor shall provide temporary means of dewatering residual solids from tank cleaning operations. Centrate or filtrate generated during dewatering may be disposed of to a plant drain, as approved by the Owner. The Owner reserves the right to disallow disposal of any waste stream that may negatively impact or impair plant operations.
E. Before any tank contents are removed from the treatment plant site, documentation shall be submitted demonstrating that the CONTRACTOR will comply with all regulations. Landfill manifests shall be provided as verification of disposal at a licensed landfill. The CONTRACTOR shall coordinate all hauling activities with the landfill.
F. Flush and drain all piping to be modified prior to construction. Contractor shall provide additional cleaning as required for proper construction.
G. Existing structures requiring cleaning prior to modifications include the following:
Structure name
Plan Dimensions (ft x ft)
Sidewall height above footing (ft)
Sidewall height above existing grade(1) (ft)
Volume of residuals (gallons) (2)
Aeration Tank No. 1
Pass No. 1
154 x 40
19
10 – 17
61,300
Pass No. 2
154 x 40
19
11 – 18
61,300
Pass No. 3
154 x 40
19
12 – 18
61,300
Aeration Tank No. 2
Pass No. 1
154 x 40
19
9 – 16
61,300
Pass No. 2
154 x 40
19
9 – 15
61,300
Pass No. 3
154 x 40
19
8 – 15
61,300
Aeration Tank No. 3
Pass No. 1
154 x 40
19
10 – 14
61,300
Pass No. 2
154 x 40
19
12 – 15
61,300
Pass No. 3
154 x 40
19
12 – 15
61,300
Aerobic Digester No. 1
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 2
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 3
72 x 40
19.5
9.5 – 14.5
27,000
Aerobic Digester No. 4
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 5
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 6
72 x 40
19.5
10.5 – 14.5
27,000
Aerobic Digester No. 7
72 x 40
19.5
11.5 – 14.5
27,000
Aerobic Digester No. 8
72 x 40
19.5
11.5 – 14.5
27,000
(1) Varies
(2) Volume of residuals to be removed calculated to the top of the existing diffuser elements.
3.2 CLEANING DURING CONSTRUCTION
A. Execute periodic cleaning to keep Work, site, and adjacent properties free from accumulations of waste materials, rubbish, and windblown debris resulting from construction operations.
B. Provide on-site containers for collection and removal of waste materials, debris, and rubbish in accordance with applicable regulations. Remove weekly and dispose of off- site.
C. Thoroughly clean all spilled dirt, gravel, or other foreign material caused by the construction operations from all streets and roads at the conclusion of each day's operation.
D. Provide daily cleaning of facilities in use by the Owner when construction dust, mud or debris interfere with the Owner’s operations.
E. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.
F. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.
3.3 DUST CONTROL
A. Clean interior space prior to start of finish painting and continue cleaning on as-needed basis until painting is completed.
B. Schedule operations so dust and other contaminants resulting from cleaning process will not fall on wet or newly coated surfaces.
C. Give all roads and haul roads used in the construction area an approved dust-preventive treatment and/or daily watering when requested by the Engineer to prevent dust. Applicable environmental regulations for dust prevention shall be strictly enforced.
3.4 FINAL CLEANING
A. Employ skilled workers for final cleaning.
A.
B. Execute final cleaning prior to final inspection.
C. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
D. Clean all interior walls, ceilings, floors, cabinets, and furniture.
E. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
F. Wash and shine glazing and mirrors.
G. Polish glossy surfaces to clear shine.
H. Ventilating Systems:
1. Clean permanent filters and replace disposable filters if units were operated during construction.
2. Clean ducts, blowers, and coils if units were operated without filters during construction.
I. Electrical Systems:
1. Leave electrical equipment rooms broom clean.
2. Clean interior of panel cabinets, pull boxes, and other equipment enclosures.
3. Wash and wipe clean lighting fixtures, lamps, and other electrical equipment that may have become soiled during installation.
4. Touch-up paint and repaint, if deterioration is extensive, electrical items delivered to job with finish coat of paint.
J. Clean debris from roofs, gutters, down spouts, and drainage systems.
K. Clean site; sweep paved areas, rake clean landscaped surfaces.
L. Remove waste and surplus materials, rubbish and construction from the site.
END OF SECTION
SECTION 01700 CONTRACT CLOSEOUT
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01700 CONTRACT CLOSEOUT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Closeout procedures.
B. Final cleaning.
C. Adjusting.
D. Project record documents.
E. Operation and maintenance data.
F. Warranties.
G. Spare parts and maintenance materials.
1.2 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's inspection.
B. Provide submittals to Engineer that are required by governing or other authorities.
C. Submit final Application for Payment as specified in the GENERAL CONDITIONS identifying total adjusted Contract Price, previous payments, and amount remaining due. Included with the final Application for payment shall be the following written certifications:
1. Final waiver of liens from Contractor, all subcontractors and all material and equipment suppliers.
2. Contractor's affidavit of release of liens.
3. Consent of surety for final payment.
4. Contractor's affidavit of payment.
5. Affidavit of compliance with wage rate determination in accordance with Division 0.
1.3 FINAL CLEANING
A. Final cleaning as specified in Section 01710 - Cleaning.
A.
1.4 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.5 PROJECT RECORD DOCUMENTS
A. Project Record Documents are to be submitted as specified in Section 01720 - Project Record Documents.
1.6 OPERATION AND MAINTENANCE DATA
A. Operation and maintenance data are to be submitted as specified in Section 01730 - Operation and Maintenance Data.
1.7 WARRANTIES AND BONDS
A. Provide notarized copies.
B. Execute and assemble documents from Subcontractors, suppliers, and manufacturers.
C. Provide Table of Contents and assemble in three ring binders with durable plastic covers.
D. Submit to Engineer for approval prior to final Application for Payment.
E. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period.
1.8 SPARE PARTS AND MAINTENANCE MATERIALS
A. Provide products, spare parts, maintenance and extra materials in quantities specified in individual specification Sections.
B. Deliver to Project site and place in location as directed; obtain receipt prior to final payment. Fill out and submit to the Owner the attached Spare Parts Transfer Form for each parcel of spare parts delivered.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
SECTION 01700 CONTRACT CLOSEOUT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Closeout procedures.
B. Final cleaning.
C. Adjusting.
D. Project record documents.
E. Operation and maintenance data.
F. Warranties.
G. Spare parts and maintenance materials.
1.2 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's inspection.
B. Provide submittals to Engineer that are required by governing or other authorities.
C. Submit final Application for Payment as specified in the GENERAL CONDITIONS identifying total adjusted Contract Price, previous payments, and amount remaining due. Included with the final Application for payment shall be the following written certifications:
1. Final waiver of liens from Contractor, all subcontractors and all material and equipment suppliers.
2. Contractor's affidavit of release of liens.
3. Consent of surety for final payment.
4. Contractor's affidavit of payment.
5. Affidavit of compliance with wage rate determination in accordance with Division 0.
1.3 FINAL CLEANING
A. Final cleaning as specified in Section 01710 - Cleaning.
A.
1.4 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.5 PROJECT RECORD DOCUMENTS
A. Project Record Documents are to be submitted as specified in Section 01720 - Project Record Documents.
1.6 OPERATION AND MAINTENANCE DATA
A. Operation and maintenance data are to be submitted as specified in Section 01730 - Operation and Maintenance Data.
1.7 WARRANTIES AND BONDS
A. Provide notarized copies.
B. Execute and assemble documents from Subcontractors, suppliers, and manufacturers.
C. Provide Table of Contents and assemble in three ring binders with durable plastic covers.
D. Submit to Engineer for approval prior to final Application for Payment.
E. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period.
1.8 SPARE PARTS AND MAINTENANCE MATERIALS
A. Provide products, spare parts, maintenance and extra materials in quantities specified in individual specification Sections.
B. Deliver to Project site and place in location as directed; obtain receipt prior to final payment. Fill out and submit to the Owner the attached Spare Parts Transfer Form for each parcel of spare parts delivered.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
END OF SECTION
SECTION 01660 WATER TEST FOR CONCRETE TANKS
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01660
WATER TEST FOR CONCRETE TANKS
PART 1 GENERAL
1.1 DESCRIPTION
A. This section includes leakage testing for all new liquid holding concrete tanks.
1.2 TEST CONDITIONS
A. Conduct test prior to backfilling and prior to coating tank.
B. Test shall not be started prior to concrete obtaining its 28 day strength.
C. Water for testing: Treated plant effluent is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) and / or non-potable water (W2) is available for use by the Contractor. Contractor shall pay costs of W1 and W2 water directly to the Owner. Contractor shall provide temporary pumping and piping facilities to transport water as required. Disposal of water used in testing shall be the Contractor's responsibility.
1.3 TEST CRITERION
A. Water Leakage Tests - All Water-Holding Structures:
1. All new water-holding structures shall be subjected to leakage tests after the concrete has been cured and obtained its design strength, and before backfill, brick facing, or other work that will cover the exposed faces of the walls is begun.
2. All basins to be subjected to leakage tests shall be filled with water to the normal liquid level line. After the basin has been kept full for 48 hours, it will be assumed for the purposes of the test that the absorption of moisture by the concrete in the basin is complete. All valves and gates to the structure shall then be closed and the change in water surface measured for a 24-hour period.
3. During the test period, all exposed portions of the structure shall be examined and all visible leaks or damp spots shall be marked; such leaks or damp spots shall be later patched or corrected in a manner acceptable to the Engineer. If the drop in water surface in the 24-hour period exceeds 1/10 of 1 percent of the normal volume of liquid contained in the water-holding structure, after accounting for evaporation and precipitation in open basins, the leakage shall be considered excessive. Evaporation shall be determined by floating an evaporation pan in the structure during the test period.
4. If the leakage is excessive, the basin shall be drained, all leaks previously marked shall be patched, and the necessary repairs made. The Contractor's method of repair shall be subject to the requirements of these Specifications and submitted for review by the Engineer.
5. The basin shall then be refilled and again tested for leakage. This process shall be continued until the drop in water surface in a 24-hour period with the basin full is less than 1/10 of 1 percent of the volume of liquid held in the basin. All
1.
repairs of faulty workmanship and materials, as well as additional testing, shall be made by the Contractor in an acceptable manner at no additional cost to the Owner. Both the correction for excessive leakage and the removal of the damp or wet spots on walls shall be required to pass the leakage test.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 TEST PROCEDURE
A. Fill tank to intended operating level:
1. Compute volume of tank to this level.
B. Measure water elevation on each tank wall at four equidistant points and average readings:
1. Provide stilling wells at each measuring point to dampen wave action.
2. Make measurements to 0.005 feet.
C. At end of test period measure water elevation to determine loss or gain volumetrically:
1. Correct for evaporation and rainfall.
D. Tanks initially passing leakage test shall have all visible leaks repaired prior to coating.
E. Perform following to tanks not meeting allowable leakage:
1. Locate leaks.
2. Drain tank and repair leaks.
3. Submit methodology and proposed materials for repairing of leaks to Engineer for review. Engineer will determine acceptability of proposed methods and materials.
4. Repair cracks.
5. Refill and retest tank.
6. Repeat repairing and testing procedures as many times as necessary to meet allowable leakage.
F. Water leakage testing shall be performed on the following structures:
1. RAS Denitrification Tank (Structure #32)
END OF SECTION
SECTION 01660
WATER TEST FOR CONCRETE TANKS
PART 1 GENERAL
1.1 DESCRIPTION
A. This section includes leakage testing for all new liquid holding concrete tanks.
1.2 TEST CONDITIONS
A. Conduct test prior to backfilling and prior to coating tank.
B. Test shall not be started prior to concrete obtaining its 28 day strength.
C. Water for testing: Treated plant effluent is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) and / or non-potable water (W2) is available for use by the Contractor. Contractor shall pay costs of W1 and W2 water directly to the Owner. Contractor shall provide temporary pumping and piping facilities to transport water as required. Disposal of water used in testing shall be the Contractor's responsibility.
1.3 TEST CRITERION
A. Water Leakage Tests - All Water-Holding Structures:
1. All new water-holding structures shall be subjected to leakage tests after the concrete has been cured and obtained its design strength, and before backfill, brick facing, or other work that will cover the exposed faces of the walls is begun.
2. All basins to be subjected to leakage tests shall be filled with water to the normal liquid level line. After the basin has been kept full for 48 hours, it will be assumed for the purposes of the test that the absorption of moisture by the concrete in the basin is complete. All valves and gates to the structure shall then be closed and the change in water surface measured for a 24-hour period.
3. During the test period, all exposed portions of the structure shall be examined and all visible leaks or damp spots shall be marked; such leaks or damp spots shall be later patched or corrected in a manner acceptable to the Engineer. If the drop in water surface in the 24-hour period exceeds 1/10 of 1 percent of the normal volume of liquid contained in the water-holding structure, after accounting for evaporation and precipitation in open basins, the leakage shall be considered excessive. Evaporation shall be determined by floating an evaporation pan in the structure during the test period.
4. If the leakage is excessive, the basin shall be drained, all leaks previously marked shall be patched, and the necessary repairs made. The Contractor's method of repair shall be subject to the requirements of these Specifications and submitted for review by the Engineer.
5. The basin shall then be refilled and again tested for leakage. This process shall be continued until the drop in water surface in a 24-hour period with the basin full is less than 1/10 of 1 percent of the volume of liquid held in the basin. All
1.
repairs of faulty workmanship and materials, as well as additional testing, shall be made by the Contractor in an acceptable manner at no additional cost to the Owner. Both the correction for excessive leakage and the removal of the damp or wet spots on walls shall be required to pass the leakage test.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
3.1 TEST PROCEDURE
A. Fill tank to intended operating level:
1. Compute volume of tank to this level.
B. Measure water elevation on each tank wall at four equidistant points and average readings:
1. Provide stilling wells at each measuring point to dampen wave action.
2. Make measurements to 0.005 feet.
C. At end of test period measure water elevation to determine loss or gain volumetrically:
1. Correct for evaporation and rainfall.
D. Tanks initially passing leakage test shall have all visible leaks repaired prior to coating.
E. Perform following to tanks not meeting allowable leakage:
1. Locate leaks.
2. Drain tank and repair leaks.
3. Submit methodology and proposed materials for repairing of leaks to Engineer for review. Engineer will determine acceptability of proposed methods and materials.
4. Repair cracks.
5. Refill and retest tank.
6. Repeat repairing and testing procedures as many times as necessary to meet allowable leakage.
F. Water leakage testing shall be performed on the following structures:
1. RAS Denitrification Tank (Structure #32)
END OF SECTION
SECTION 01650 STARTING OF SYSTEMS
This spec was part of the Des Plaines, IL River WRF project that bid Feb 26, 2015.
SECTION 01650 STARTING OF SYSTEMS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Starting equipment and systems.
B. Operator training.
C. Plant start-up.
D. Testing, Adjusting and Balancing.
1.2 STARTING EQUIPMENT AND SYSTEMS
A. Startup: Systematic process of ensuring systems perform interactively according to design intent and Owner’s operational needs. Startup process encompasses and coordinates system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training, and verification of actual performance.
B. Provide a schedule for start-up for each new system or facility. Schedules shall conform to Section 01323 and shall provide sufficient detail for a logical sequence of tasks leading to start-up. Start-up schedule shall be submitted to Architect/Engineer 30 days prior to start-up.
C. Coordinate schedule for start-up of various equipment and systems.
D. Notify Engineer seven days prior to start-up of each item.
E. Conduct progress startup meetings throughout construction, to plan, scope, coordinate, schedule future activities and resolve problems.
F. Verify that all O&M manuals have been submitted and approved in accordance with Section 01730.
G. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or other conditions that may cause damage.
H. Verify that tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.
I. Verify wiring and support components for equipment are complete and tested.
J. Execute start-up under supervision of responsible manufacturer's representative in accordance with manufacturers' instructions.
A.
K. Require manufacturer to provide authorized representative to be present at site to inspect, check and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
L. Submit a written report in accordance with Section 01445 that equipment or system has been properly installed and is functioning correctly.
1.3 OPERATOR TRAINING
A. Operator training shall conform to the requirements of Section 01445.
B. Demonstrate operation and maintenance of equipment and products to Owner's personnel at least 14 days prior to start-up.
C. Demonstrate Project equipment and instruct in a classroom environment located at the treatment plant and instructed by a manufacturers' representative who is knowledgeable about the Project.
D. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
E. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
F. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled times, at designated location.
G. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
H. The amount of time required for operator training on each item of equipment and system is that specified in individual sections.
1.4 PLANT START-UP
A. Clear Water Test Period:
1. The Clear Water Test shall simulate full-scale plant operations with all tanks, basins, pipelines, and equipment in service for a minimum 3 consecutive days. Water for Testing: Treated plant effluent (W3) is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) or nonpotable water (W2) may also be available for use by the Contractor. Contractor shall pay costs of W1 and W2 water directly to the Owner. Dispose of test water by pumping to the plant drain system. Disposal of water used in testing shall be the Contractor's responsibility.
2. The Clear Water Test shall not commence until:
a. Manufacturer's Certificates of Proper Installation have been provided for all installed equipment.
b. Pipeline pressure tests have been completed.
a.
c. Equipment has been lubricated in conformance with the manufacturer's recommendations.
d. All functional testing has been completed.
e. All performance testing has been completed, except for testing that the Engineer accepts to be performed during the clear water test.
f. The process instrumentation and control systems have been completed in accordance with all of Division 1 and 13 requirements. The Operational Readiness Test has been substantially completed and documented.
g. All tests, adjustments, and settings have been performed on electrical equipment.
h. All operations and maintenance manuals have been approved by the Engineer.
3. Clear water testing of all new equipment and systems is required. Fill tanks to the maximum operating level and operate all pumps and associated equipment.
4. During execution of the clear water test, specified pump performance and field tests and other tests approved by the Engineer may be performed.
5. Contractor shall correct equipment and system deficiencies that arise during clear water testing.
B. Wastewater Start-up Period:
1. Start-up of the new facilities with wastewater includes coordinated operation of the facilities by the Contractor, his subcontractors, Owner-operating personnel, and manufacturer's representatives for equipment items and systems.
2. The Contractor shall provide the following services.
a. Provide the coordinated services of all subcontractors and equipment suppliers to correct any and all observed and experienced deficiencies in the specified services completed or yet to be performed.
b. Complete testing on specified items, such as pumps, and coordinate with the Owner's operation of such equipment.
c. Complete the instrumentation system functional acceptance test.
d. Provide the services of a project superintendent to manage any contract change orders during start-up.
3. The Contractor shall designate and provide one or more persons to be responsible for coordinating and expediting his start-up duties. The person or persons shall be present during all prestart-up meetings and shall be available to the Owner's personnel at all times during the wastewater start-up period.
4. Where start-up services are called for in the Specifications, the Contractor shall supply and coordinate the specified manufacturers' services for the start-up period.
5. The Contractor shall conduct performance tests on all equipment, systems, and subsystems not previously tested and approved by the Engineer.
6. The Contractor shall be responsible for adjustments, repairs, and corrections of specified work.
7. The Owner will provide and pay for the necessary electrical service and chemicals used during the wastewater start-up and operation periods. The Contractor shall coordinate the procurement and delivery of such items with the Owner.
8. Following the successful start-up of plant facilities on wastewater, the Owner will assume full responsibilities for all operations, maintenance and process
1.
adjustments. The Contractor, subcontractors, and equipment manufacturer(s) shall only be responsible for specified warranty work, uncompleted work and remaining training services.
9. Provide skilled trades crew for performance of work as directed by the Engineer during startup. This work is in addition to the Contractor’s specified responsibilities, and will be paid for from the Allowances (if applicable). Contractor shall have prior approval from the Engineer prior to performing work under this allowance.
10. Successful completion of Startup is required prior to Substantial Completion.
1.5 TESTING, ADJUSTING AND BALANCING
A. Contractor will appoint and employ services of independent firm to perform testing, adjusting, and balancing. Contractor shall pay for services.
B. Independent firm will perform services specified in Division 15.
C. Reports will be submitted by independent firm to Architect/Engineer indicating observations and results of tests and indicating compliance or non-compliance with requirements of Contract Documents.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01650 STARTING OF SYSTEMS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Starting equipment and systems.
B. Operator training.
C. Plant start-up.
D. Testing, Adjusting and Balancing.
1.2 STARTING EQUIPMENT AND SYSTEMS
A. Startup: Systematic process of ensuring systems perform interactively according to design intent and Owner’s operational needs. Startup process encompasses and coordinates system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training, and verification of actual performance.
B. Provide a schedule for start-up for each new system or facility. Schedules shall conform to Section 01323 and shall provide sufficient detail for a logical sequence of tasks leading to start-up. Start-up schedule shall be submitted to Architect/Engineer 30 days prior to start-up.
C. Coordinate schedule for start-up of various equipment and systems.
D. Notify Engineer seven days prior to start-up of each item.
E. Conduct progress startup meetings throughout construction, to plan, scope, coordinate, schedule future activities and resolve problems.
F. Verify that all O&M manuals have been submitted and approved in accordance with Section 01730.
G. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or other conditions that may cause damage.
H. Verify that tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.
I. Verify wiring and support components for equipment are complete and tested.
J. Execute start-up under supervision of responsible manufacturer's representative in accordance with manufacturers' instructions.
A.
K. Require manufacturer to provide authorized representative to be present at site to inspect, check and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
L. Submit a written report in accordance with Section 01445 that equipment or system has been properly installed and is functioning correctly.
1.3 OPERATOR TRAINING
A. Operator training shall conform to the requirements of Section 01445.
B. Demonstrate operation and maintenance of equipment and products to Owner's personnel at least 14 days prior to start-up.
C. Demonstrate Project equipment and instruct in a classroom environment located at the treatment plant and instructed by a manufacturers' representative who is knowledgeable about the Project.
D. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
E. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
F. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled times, at designated location.
G. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
H. The amount of time required for operator training on each item of equipment and system is that specified in individual sections.
1.4 PLANT START-UP
A. Clear Water Test Period:
1. The Clear Water Test shall simulate full-scale plant operations with all tanks, basins, pipelines, and equipment in service for a minimum 3 consecutive days. Water for Testing: Treated plant effluent (W3) is available for use by the Contractor. Contractor shall provide temporary pumping and piping facilities to transport water. City water (W1) or nonpotable water (W2) may also be available for use by the Contractor. Contractor shall pay costs of W1 and W2 water directly to the Owner. Dispose of test water by pumping to the plant drain system. Disposal of water used in testing shall be the Contractor's responsibility.
2. The Clear Water Test shall not commence until:
a. Manufacturer's Certificates of Proper Installation have been provided for all installed equipment.
b. Pipeline pressure tests have been completed.
a.
c. Equipment has been lubricated in conformance with the manufacturer's recommendations.
d. All functional testing has been completed.
e. All performance testing has been completed, except for testing that the Engineer accepts to be performed during the clear water test.
f. The process instrumentation and control systems have been completed in accordance with all of Division 1 and 13 requirements. The Operational Readiness Test has been substantially completed and documented.
g. All tests, adjustments, and settings have been performed on electrical equipment.
h. All operations and maintenance manuals have been approved by the Engineer.
3. Clear water testing of all new equipment and systems is required. Fill tanks to the maximum operating level and operate all pumps and associated equipment.
4. During execution of the clear water test, specified pump performance and field tests and other tests approved by the Engineer may be performed.
5. Contractor shall correct equipment and system deficiencies that arise during clear water testing.
B. Wastewater Start-up Period:
1. Start-up of the new facilities with wastewater includes coordinated operation of the facilities by the Contractor, his subcontractors, Owner-operating personnel, and manufacturer's representatives for equipment items and systems.
2. The Contractor shall provide the following services.
a. Provide the coordinated services of all subcontractors and equipment suppliers to correct any and all observed and experienced deficiencies in the specified services completed or yet to be performed.
b. Complete testing on specified items, such as pumps, and coordinate with the Owner's operation of such equipment.
c. Complete the instrumentation system functional acceptance test.
d. Provide the services of a project superintendent to manage any contract change orders during start-up.
3. The Contractor shall designate and provide one or more persons to be responsible for coordinating and expediting his start-up duties. The person or persons shall be present during all prestart-up meetings and shall be available to the Owner's personnel at all times during the wastewater start-up period.
4. Where start-up services are called for in the Specifications, the Contractor shall supply and coordinate the specified manufacturers' services for the start-up period.
5. The Contractor shall conduct performance tests on all equipment, systems, and subsystems not previously tested and approved by the Engineer.
6. The Contractor shall be responsible for adjustments, repairs, and corrections of specified work.
7. The Owner will provide and pay for the necessary electrical service and chemicals used during the wastewater start-up and operation periods. The Contractor shall coordinate the procurement and delivery of such items with the Owner.
8. Following the successful start-up of plant facilities on wastewater, the Owner will assume full responsibilities for all operations, maintenance and process
1.
adjustments. The Contractor, subcontractors, and equipment manufacturer(s) shall only be responsible for specified warranty work, uncompleted work and remaining training services.
9. Provide skilled trades crew for performance of work as directed by the Engineer during startup. This work is in addition to the Contractor’s specified responsibilities, and will be paid for from the Allowances (if applicable). Contractor shall have prior approval from the Engineer prior to performing work under this allowance.
10. Successful completion of Startup is required prior to Substantial Completion.
1.5 TESTING, ADJUSTING AND BALANCING
A. Contractor will appoint and employ services of independent firm to perform testing, adjusting, and balancing. Contractor shall pay for services.
B. Independent firm will perform services specified in Division 15.
C. Reports will be submitted by independent firm to Architect/Engineer indicating observations and results of tests and indicating compliance or non-compliance with requirements of Contract Documents.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
Subscribe to:
Posts (Atom)