Section 15116
TELESCOPING VALVE
PART 1 – GENERAL
1.1 THE REQUIREMENT
A. The Contractor shall provide
telescoping valve, complete with valve stand, rack and pinion
adjusting mechanism, guide pipe and bail, slip pipe and bail and
companion flange, spare parts and appurtenances in accordance with
the Contract Documents.
1.2 REFERENCE SPECIFICATIONS,
CODES AND STANDARDS
A. The work of the following sections
applies to the work of this Section. Other sections of the
Specifications, not referenced below, shall also apply to the extent
required for proper performance of this work:
1. General Conditions
2. Section 15100, Valves,
General
3. Section 15101, Valve and
Gate Operators
1.3 SUBMITTALS
A. In addition to the requirements of
Section 15100 and the material listed in the detailed specification,
the following shall be submitted in accordance with Section 01300:
1. Complete assembly and
installation drawings showing dimensional layout, materials of
construction, applicable material standards, equipment details and
appurtenances.
2. Manufacturer literature and
catalog cut sheets.
3. Manufacturer’s
installation instructions.
4. Manufacturer’s O&M
manuals as specified in Section 01300.
PART 2 – PRODUCTS
2.1 PERFORMANCE AND DESIGN REQUIREMENTS
A. Digester Supernatant Telescoping Valve
1. General
a. Number of Units: 1 b.
Location: Digester 2
c. Service: Digested Sludge
2.2
GENERAL
A. Valve Stand and Operator
1. Valve stand shall be of heavy cast
iron construction with base mounting flange, operating crank handle,
cut steel rising rack, cut steel pinion, and rack stop.
2. A stainless steel guide pipe shall
connect the rack to the bail that connects to the slip pipe.
3. The pinion gearing shall be designed
so that each complete revolution produces a valve travel of
approximately 4-3/4 inches.
B. Guide Pipe and Bail: Guide
pipe and bail shall be made from Type 304 stainless steel.
One end of the guide pipe shall thread
into the bottom of the rack while the other end threads into the
bail.
C. Slip Pipe: The slip pipe shall be
fabricated from Type 304 stainless steel tubing. Top of pipe shall
have a V-notch weir for flow control. The length of the pipe shall
be sufficient to allow the full required travel with an
additional 6 inches remaining below the companion flange to
provide adequate support. The slip pipe shall be bolted to the bail.
D. Companion Flange: Manual
telescoping valve shall be furnished with a type 304
stainless steel companion flange designed to match a stainless steel
pipe flange and bored with sufficient clearance to allow the slip
tube to slide but no sludge to escape. Each companion flange shall be
furnished with two (2) sealing gaskets of Neoprene rubber having an
inner diameter slightly smaller than the outer diameter of the slip
tube. The Contractor shall furnish the companion flange mounting
bolts.
1. The Contractor shall accept unit
responsibility to ensure that fabrication of the supernatant box
mounting flange and telescoping valve companion flange are
compatible.
2.3 ANCHOR BOLTS, EMBEDDED ITEMS,
AND FASTENERS
A. All anchor bolts, anchor
sleeves, fasteners, hardware and embedded items shall be type
316 stainless steel and conform to the
requirements of Section 05500.
2.4 PROTECTIVE COATINGS
A. All equipment and piping
shall be coated in accordance with Section 09800.
2.5 MANUFACTURERS
A. Telescoping valves shall be
manufactured by one of the following:
1. Amwell
2. Or Approved Equal
PART 3 –
EXECUTION
3.1 DELIVERY, STORAGE AND
HANDLING
A. All equipment and parts shall be
properly protected so that no damage or deterioration will occur
during a prolonged delay from the time of shipment until
installation is completed and the units and equipment are ready for
operation.
B. All equipment and parts shall
be properly protected against any damage during a prolonged
period at the site.
3.2 INSTALLATION
A. Verify that dimensions are correct
and project conditions are suitable for installation. Do not proceed
with installation until unsatisfactory conditions have been
corrected.
B. Install the telescoping valve in
accordance with manufacturer's instructions. Adjust to provide smooth
operation.
C. If the gate does not function
properly to the satisfaction of the Resident Project
Representative, The Contractor shall necessary modification and
corrections at not additional cost to the District.
END OF SECTION
No comments:
Post a Comment