Section 16010
ELECTRICAL GENERAL PROVISIONS
PART 1 - GENERAL
1.1 THE REQUIREMENT A. General
1. The Contractor shall provide all
tools, supplies, materials, equipment, and all labor necessary for
the furnishing, construction, installation, testing, and
operation of all electrical work and appurtenant work necessary to
provide a complete and operable system, all in accordance with the
requirements of the Contract Documents.
2. The provisions of this Section shall
apply to all electrical items specified in the various sections of
Division 16 and all other Divisions specifying electrical items of
these Specifications, except where otherwise specified or
shown in the Contract Documents.
B. Responsibility
1. The Contractor shall be
responsible for:
a. Complete systems in
accordance with the intent of these Contract
Documents.
b. Coordinating the incoming
electrical service with the electric utility company providing
service.
c. Coordinating the details of facility
equipment and construction for all Specification Divisions which
affect the work covered under Division 16, Electrical.
d. Furnishing and installing all
incidental items not actually shown or specified, but which are
required by good practice to provide complete functional systems.
e. The Contractor shall lay out
electrical work prior to placing floors and walls to properly locate
all penetrations, and shall furnish and install all sleeves and
openings required for passage of all raceways.
f. The Contractor shall furnish and
install all inserts and hangers required to support raceways and
other electrical equipment and materials.
g. The Contractor shall notify
the Resident Project Representative in writing
48 hours in advance of energizing any
new electrical equipment. If the energization is rescheduled later
than 48 hours from the originally scheduled time, a new notification
shall be made. The Contractor shall
not proceed without approval from the
Resident Project Representative.
h. Temporary
Power: The Contractor shall furnish, install and maintain all
temporary power and lighting systems needed for construction. This
temporary system shall include weatherproof panel(s) for
the Contractor's main circuit breakers and power distribution system,
and ground fault interrupting equipment. All connections shall be
watertight with Wiring done with Type SO portable cable as a minimum.
The Contractor shall remove all temporary power equipment and
devices after construction is completed.
i. Electrical System Protective Device
Coordination: During the Contract period, the Engineer shall
perform a preliminary and a final coordination study to determine the
proper settings for all protective relays, circuit breakers and
fuses. This study may include all devices starting at the utility
service, and including the secondary devices on all transformers, and
extending to include all feeder and branch circuits, including low-
voltage circuits from 120 V to 480 V. This study may be completed
for both short-circuit and ground fault protective devices. The
Contractor shall provide complete cooperation to the Owner to support
any such effort.
C. Existing Conditions
1. The existing electrical drawings
were developed based on available record drawings furnished by
the Owner. The Contractor is warned that the locations of existing
buried conduits and ductbanks shown may differ from the
actual locations. The Contractor shall take all necessary measures
to protect existing buried utilities when making excavations.
2. Carry out any work involving the
shutdown of existing services to any piece of equipment now
functioning or the tie-in of equipment to the existing system at such
time as to provide the least amount of inconvenience to the Owner. Do
such work when directed by the Resident Project Representative and
only after the new facility or system is operational and has been
tested.
3. Construction Coordination and
Electrical Downtime: See the “Protection and/or Relocation of
Utilities” in the General Conditions of these Specifications
regarding scheduling of electric power interruptions.
a. Before any work is performed in
manholes containing medium voltage circuits, these circuits shall be
de-energized. All such efforts must be coordinated with the
Resident Project Representative.
b. After award of Contract, confer with
Resident Project Representative to verify each area of construction
activity and location of existing underground utilities. Protect
all existing underground utilities during construction.
4. No work shall be started without
first obtaining and completing all coordination forms required by the
Owner. All such coordination forms shall be submitted with drawings
and procedures showing information about what, where, why and how the
work will be done in accordance with the General Conditions.
5. Prior to
staring any underground work the Contractor shall notify the Resident
Project Representative and take proper precaution to locate
the utilities by ground survey using aboveground features,
potholing or employing other means such as magnetic utility locating
instruments.
6. The Contract Documents are not
intended to show every offset and fitting, or every structural and
mechanical obstruction that will be encountered during the
installation of the work. The alignment of equipment and raceways
shall be varied due to architectural or structural changes, or to
avoid conflict with other trades. Electrical system installations
shall be integrated with all existing facilities and the work of
other disciplines in this Contract. Accommodation of existing
conditions and conditions developed by the Contractor shall be at no
extra cost to the Owner.
All raceway sizes and numbers of cables
and conductors in each raceway, as shown on the Contract Documents,
may vary in accordance with actual field conditions and equipment
installed. The Contractor shall make all changes required at no
extra cost to the Owner. See Section 16220 of these
Specifications for additional requirements for motor installation.
7. The equipment to be furnished under
this specification shall meet the seismic requirements outlined in
the Uniform Building Code, for Occupancy Category I, Essential
Services, in Seismic Zone 4.
All electrical equipment and materials
shall be capable of operating successfully at full-rated load,
without failure, at an ambient temperature of 40°C (104°F).
8. A Material Safety Data Sheet (MSDS)
shall be provided for each type of paint solvent, cleaner, oil, etc.
supplied. See Section 09800 of these Specifications for South Coast
Air Quality Management District (SCAQMD) reporting requirements.
D. Intent of Drawings: Electrical plan
drawings show only general locations and alignments of equipment,
devices, and raceway, unless specifically dimensioned. The
Contractor shall be responsible for the proper routing of raceway,
subject to the approval of the Resident Project Representative.
1.2 RELATED WORK SPECIFIED
ELSEWHERE
A. The work of the following divisions
or sections applies to the work of this Section. Other sections of
the Specifications, not referenced below, shall also apply to
the extent required for proper performance of this work.
1. Section 01660, Installation,
Testing, Commissioning and Training
2. Section 02200, Earthwork
3. Section 09800, Protection
4. Division 11 Equipment
5. Division 15 Mechanical
6. Division 17 Instrumentation
and Control
7.
Work Specified Under Other Divisions
a. All concrete work required for
encasement, installation, or construction of the work specified in
the various sections of Division 16 is included as a part of the work
hereunder, and shall be 2500 psi concrete conforming to the
applicable requirements of Section 03300, provided, that the
following exceptions and supplementary requirements shall apply:
(1) Consolidation of encasement
concrete around duct banks shall be by hand puddling, and/or
mechanical vibration.
(2) A workability admixture shall be
used in encasement concrete, which shall be a hydroxylated carboxylic
acid type in liquid form. Admixtures containing calcium chloride
shall not be used.
(3) Concrete for encasement of conduit
or duct banks shall contain an integral red-oxide coloring pigment in
the proportion of 8 pounds per cubic yard of concrete.
1.3 REFERENCE SPECIFICATIONS,
CODES AND STANDARDS
A. All electrical equipment and
materials shall be designed, manufactured and installed in accordance
with the latest published edition of the applicable standards of the
following standards making organizations. Specific standards are
identified in the various sections for specific types of equipment
and materials.
IEEE Institute of
Electrical and Electronic Engineers (IEEE) ANSI
American National Standards Institute (ANSI)
NEMA National Electrical
Manufacturers Association (NEMA) ASTM American Society
for Testing and Materials (ASTM) ICEA Insulated Cable
Engineers Association (ICEA)
NETA International
Electrical Testing Association (NETA) AEIC
Association of Edison Illuminating Companies (AEIC) UL
Underwriters Laboratories, Inc. (UL)
FM Factory Mutual
Research Corp. (FM) CSA Canadian Standards
Association (CSA)
B. Without limiting the generality of
other requirements of these Specifications, all work specified herein
shall conform to or exceed the applicable requirements of the
National Electric Code (NEC); provided, where a local code or
ordinance is in conflict with the NEC, the provisions of said local
code ordinance shall take precedence.
C. All work specified herein shall
conform to or exceed the applicable requirements of the referenced
portions of the following publications to the extent that the
provisions thereof are not in conflict with other provisions of these
Specifications.
1. Codes
and Standards: Electrical work, including connection to
electrical equipment integral with mechanical equipment described
elsewhere in these Specifications, shall be performed in accordance
with the latest published edition of the following codes:
NEC National Fire Protection Agency
(NFPA) –70 National Electrical Code (NEC), and 820 Standard for
Fire Protection in Wastewater Treatment and Collection Facilities,
latest adopted edition.
CCR Title 8,
Industrial Relations, Subchapter 5, Electrical Safety
Orders, California Code of Regulations.
CCR Title 24, Part
3, State Electrical Code, California Code of
Regulations (CCR),
UBC Uniform Building
Code (UBC)
2. Commercial Standards: Material,
equipment, and construction, installation, and testing procedures
shall conform to applicable standards of NEMA, ANSI, and IEEE except
where modified or supplemented by these Specifications.
D. All equipment furnished by the
Contractor shall be listed by and shall bear the label of
Underwriters' Laboratories, Incorporated, and (UL) or of an
independent testing laboratory acceptable to the Owner.
1. Identification of Listed Products:
Electrical equipment and materials shall be listed for the purpose
for which they are to be used by an independent testing
laboratory. Three such organizations are Underwriters
Laboratories (UL), Factory Mutual Research Corp. (FM), and Canadian
Standards Association (CSA). Independent testing laboratories to be
are acceptable by the Engineer.
E. The construction and installation of
all electrical equipment and materials shall comply with all
applicable provisions of the Cal/OSHA Safety orders (Title 8,
CCR), State Building Standards, and applicable local codes and
regulations.
F. Control panel elementary diagrams
shall be based on the contract drawings. Provide control panel
design, elementary diagrams, electronic diagrams, block and
logic diagrams, panel layouts, and interconnection diagrams.
1.4 CONTRACTOR SUBMITTALS
A. Submittals shall be made in
accordance with the General Requirements.
B. The Contractor shall submit complete
material lists for the work of this Section. Such lists shall state
manufacturer and brand name of each item or class of material. The
Contractor shall also submit shop drawings for all grounding work.
C. Shop drawings are required
for materials and equipment listed in this and other sections.
Shop drawings shall provide sufficient
information to evaluate the suitability of the proposed material or
equipment for the intended use, and for compliance with these
Specifications. The following shall be included:
1. Front, side, and rear
elevations, footprints and top views, with dimensions.
2.
Location and size of conduit entrances and access plates.
3. Component data.
4. Connection diagrams, terminal
diagrams, schematic wiring diagrams, conductor size, and type, etc.
5. Method of anchoring and
embedding structural members.
6. Finish.
7. Nameplates.
8. Temperature limitations, as
applicable.
9. Rating of equipment as per
specifications and drawings.
10. NEMA rating of enclosures.
11. Approved listing.
D. Catalog data shall be submitted to
supplement all shop drawings. Catalog cuts, bulletins, brochures, or
the like or photocopies of applicable pages thereof shall be
submitted for mass-produced, non-custom manufactured material. These
catalog data sheets shall be stamped to indicate the project name,
applicable specification section and paragraph, model number, and
options. This information shall be marked in spaces designated for
such data in the stamp.
E. Manuals: The Contractor
shall furnish manuals as specified in Section 01300.
F. Record Drawings: In addition to
the record drawings as a part of the record drawing requirements
specified in the General Requirements, the Contractor shall show
depths and routing of all concealed below-grade electrical
installations.
G. Manufacturer's Drawings: One
set of equipment manufacturer's drawings shall be submitted to
the Engineer for its records.
H. The Contractor shall obtain and
submit from the manufacturer a list of suggested spare parts for each
piece of equipment according to the provisions of SPARE PARTS of the
General Requirement. Contractor shall also furnish the name,
address, and telephone number of the nearest distributor for each
piece of equipment.
1. During the term of this Contract the
Contractor shall notify the Engineer in writing about any
manufacturer's modification of the identified spare parts, such as
part number, interchangeability, model change or others.
I. The Contractor shall coordinate all
necessary material and equipment inspection and testing with the
Owner as specified under Sampling, Testing and Fabrication Inspection
of the General Requirements and Section 16080.
J. The Contractor shall clearly state
deviations from the specifications and/or drawings on the first page
of the submittal.
K.
SUBMITTALS
In addition to the basic
information described in the General Requirements, the
Contractor shall submit the following
drawings, catalog sheets, device specifications, etc.:
1. Shop Drawings: The Contractor
shall review the Contract Documents and request any
clarification before submitting shop drawings. Shop drawings of all
electrical equipment, cable, devices, etc. shall be submitted as a
complete submittal, and shall meet the requirements of the Contract
Documents.
2. Catalog sheets for conduit, conduit
fittings, boxes, enclosures, cable tray, cable, relays, pushbuttons,
receptacles, face plates, circuit breakers, motor starters,
contactors, touchplate controls, lighting fixtures, transformers,
panelboards, switchboards, switchgear, etc. shall be submitted with
the required specification data to substantiate that each item
meets the requirements of the Contract Documents.
3. All control panel equipment
submittals shall include: equipment arrangement drawings,
including plan, side and elevation views, layout, and all item
locations, designations, and a complete nameplate, material, and item
list with part number, manufacturer, and description; control panel
elementary (schematic) diagrams showing all control items, wire
numbers, terminal numbers, interconnections with external control
items, designation of each item, and line numbers; control panel
wiring (connection) diagrams showing all connections,
devices, terminal numbers, wire size, and item designations.
These diagrams should show the various components in their relative
physical location.
4. Contract circuit number
designations shall be included on all shop drawing one-line,
three-line diagrams and control elementary (schematic) diagrams,
wherever these circuits appear.
5. Information required by the
Engineer to perform preliminary and final coordination
studies including:
a. Single-Line Diagrams: A
single-line diagram showing all protective devices and the major
distribution and utilization equipment. Single-line diagrams, as
presented on the Contract Documents, show circuit voltages (4xx
is 480 V, 3xx is 277 V, 2xx is 240 V, 1xx is 120 V), wire and conduit
sizes, circuit protection rating, and other pertinent data. Grounding
conductors are not necessarily indicated. See grounding
requirements specified in Section 16060 of these Specifications
b. Specification data sheets for
all protective devices intended to be supplied. This shall
include a description of the device, its purpose, its operational
characteristics, and its available adjustments.
c. Time-current characteristic curves
for all protective devices, including as a minimum, all relays,
circuit breakers, motor circuit protectors and fuses.
d. Device settings for all adjustable
control and protective devices provided by Contractor shall be
provided and tabulated in an organized manner by equipment tag number
and device setting. Included in this requirement are all time delay
relays, settings for control devices for heating, ventilating and
air conditioning (HVAC) systems, and other
instrumentation
and control devices necessary to operate various systems
installed.
1.5 QUALITY ASSURANCE A. General
1. Field Control of Location and
Arrangement: The drawings diagrammatically indicate the
desired location and arrangement of outlets, conduit
runs, equipment, and other items only. Exact locations shall be
determined by the Contractor in the field based on the physical size
and arrangement of equipment, finished elevations, required
clearances and other obstructions. Locations shown on the
drawings, however, shall be adhered to as closely as possible.
2. All conduit and equipment shall be
installed in such a manner as to avoid all obstructions and to
preserve headroom and keep openings and passageways clear. Lighting
fixtures, switches, convenience outlets, and similar items shall be
located within finished rooms, as shown. Where the drawings do not
indicate exact locations, the Contractor shall submit proposed
locations to the Resident Project Representative for review.
Where equipment is installed without instruction and must be moved,
it shall be moved without additional cost to the Owner.
3. Workmanship: All materials and
equipment shall be installed in accordance with printed
recommendations of the manufacturer which have been reviewed by the
Resident Project Representative. The installation shall be
accomplished by workmen skilled in this type of work and installation
shall be coordinated in the field with other trades so that
interferences are avoided.
4. All work, including installation,
connection, calibration, testing, and adjustment, shall be
accomplished by qualified, experienced personnel working under
continuous, competent supervision. The completed installation shall
display competent work, reflecting adherence to prevailing industrial
standards and methods.
5. Protection of Equipment and
Materials: The Contractor shall provide adequate means for and shall
fully protect all finished parts of the materials and equipment
against damage from any cause during the progress of the work and
until acceptable by the Resident Project Representative.
6. All materials and equipment, both in
storage and during construction, shall be covered in such a manner
that no finished surfaces will be damaged, marred, or splattered with
water, foam, plaster, or paint. All moving parts shall be kept clean
and dry.
7. The Contractor shall replace or have
refinished by the manufacturer, all damaged materials or equipment,
including faceplates of panels and switchboard sections, at no
expense to the Owner.
8. Tests:
The Contractor shall make all tests as specified. All such tests
shall be performed in the presence of the Engineer or
the Resident Project Representative. The Contractor shall
furnish all necessary testing equipment and pay all costs of tests,
including all replacement parts and labor necessary due to damage
resulting from damaged equipment or from test and correction of
faulty installation. Operational testing shall be performed on all
equipment furnished and/or connected in other sections of Division
16. Electrical and all other divisions specifying electrical items
including furnishing of support labor for testing.
9. Standard test reports for
mass-produced equipment shall be submitted along with the shop
drawing for such equipment. Test reports on testing specifically
required for individual pieces of equipment shall be submitted to the
Resident Project Representative for review prior to final acceptance
of the project.
10. Any test failure shall be
corrected in a manner satisfactory to the Engineer or the
Resident Project Representative.
11. Factory-trained technical service
representatives shall adjust, calibrate, repair, replace, modify,
etc. all faulty electrical equipment installed until the contract is
accepted by the Resident Project Representative. Factory
technical service representatives and electricians shall be provided
during start-up of all systems.
B. Area Designations
1. General: For purposes of
delineating electrical enclosure and electrical installation
requirements of this project, certain areas have been classified in
the Contract Documents as defined below. Electrical installations
within these areas shall conform to the referenced NFPA code
requirements for the area involved.
a. General Purpose Locations:
Electrical work installed in areas which are not otherwise
specifically classified shall be "General Purpose."
Workmanship and enclosures shall comply with the General Conditions
of these Specifications. Enclosures shall be NEMA Type 12 minimum.
b. Outdoor Locations: In outdoor
locations, raceway shall comply with Section 16130; entrances
shall be threaded; and fittings shall have gasketed covers.
Provisions shall be made to drain the fitting or conduit system.
Threaded fastening hardware shall be stainless steel. Mounting
brackets shall be galvanized. Attachments or welded assemblies
shall be galvanized after fabrication. Instruments and
control cabinets, panels, switchboards and motor control centers
shall be "Weatherproof NEMA Type 4X." Enclosures shall be
mounted 1/4-inch from walls to provide an air space, unless
specifically shown otherwise.
c. Damp Location: Locations which are
indoors and 2 feet below grade elevation shall have electrical
installations which conform to the requirements for outdoor
locations; except, that the air space from walls may be less than
1/4-inch and enclosures shall be NEMA Type 2. "Damp
locations" shall include pipe galleries, tunnels, and basements.
All rooms housing liquid handling equipment are also classified as
damp locations regardless of grade elevation.
d. Splash
Locations: Areas requiring splash-proof shall have electrical
installations as described for "outdoor locations".
e. Corrosive Locations: Corrosive
locations shall have stainless steel threaded hardware; all other
electrical hardware, fittings, and raceway systems shall be
PVC-coated. Enclosures shall be of fiberglass reinforced polyester
or 316 stainless steel and meet NEMA Type 4X requirements.
f. Hazardous Locations: Areas shown as
hazardous shall have electrical installations suitable for Class 1,
Divisions 1 and 2, Groups C and D locations as required under
Cal/OSHA Safety orders (Title 8, CCR). Enclosures shall be NEMA type
7.
C. Cleanup
1. In addition to the requirements of
the General Requirements, in all parts of the materials and equipment
shall be thoroughly cleaned. Exposed parts shall be thoroughly
clean of cement, plaster, and other materials. All oil and grease
spots shall be removed with a non-flammable cleaning solvent. Such
surfaces shall be carefully wiped and all cracks and corners scraped
out.
2. During the progress of the work, the
Contractor shall clean the premises and shall leave the premises and
all portions of the site free of debris.
a. Cleanliness and Housekeeping: In
each room and area that work is performed, the Contractor shall clean
each piece of electrical equipment, existing and new, both inside and
outside, and retouch the equipment to match the existing paint. The
intent of this requirement is to ensure that all electrical
equipment, including panelboards, MCCs, switchgear, and control
panels are in new condition, and to leave this equipment safe for
operators and maintenance personnel.
D. Shop Inspection: All electrical
materials and equipment shall be subject to shop inspection
by the Resident Project Representative or representative of a Testing
Agency.
PART 2 - PRODUCTS
2.1 GENERAL
A. Unless otherwise indicated, provide
all first-quality, new materials and equipment, free from any
defects, in first-class condition, and suitable for the space
provided. Provide materials and equipment listed by UL wherever
standards have been established by that agency.
B. Where two or more units of the same
class of material or equipment are required, provide products of a
single manufacturer. Component parts of materials or equipment of
the same manufacturer are preferred.
C. All electrical equipment
shall be approved by a testing laboratory recognized by the
Owner and shall conform to all
applicable requirements of the Owner.
2.2
STANDARD PRODUCTS
A. Unless otherwise indicated, provide
materials and equipment, which are the standard products of
manufacturers regularly engaged in the production of such materials
and equipment. Provide the manufacturers' latest standard design
that conforms to these Specifications.
B. Materials and Equipment: All
materials, equipment, and parts comprising any unit or part thereof
specified or indicated on the Contract Documents shall be new and
unused, of current manufacture, and of highest grade consistent with
the state-of-the-art acceptable by the Owner. Damaged materials,
equipment, and parts are considered to be used and will not be
accepted. All equipment and materials used shall be of a proven
type, and shall have a minimum of one year in service experience in
similar service to that utilized in the Contract. No prototype
equipment is to be installed. In addition, no equipment that is
being phased out of manufacture by the supplier shall be installed
during the Contract period.
C. The fabricator of major
equipment assemblies, such as distribution panelboards,
switchgear, MCCs, etc. shall also be the manufacturer of the
major devices or components contained therein.
2.3 EQUIPMENT FINISH
A. Provide materials and equipment
with manufacturers' standard finish system, in accordance with
Section 09800. Provide manufacturers' standard finish color, except
where specific color is indicated. If manufacturer has no standard
color, finish equipment in accordance with Section 09800, or with
ANSI No. 61, light gray color.
2.4 OUTDOOR EQUIPMENT
A. Provide equipment and devices to
be installed outdoors or in unheated enclosures capable of
continuous operation within an ambient temperature range of 30
degrees F to
120 degrees F.
2.5 HAZARDOUS AREAS
A. Provide materials and equipment
acceptable to the regulatory authority having jurisdiction for the
Class, Division, and Group of hazardous area indicated.
2.6 EXIT SIGNS
A. Provide internally
illuminated exit signs in accordance with UFC 1212 and UBC Section
1003.2.8. Provide two separate sources
of power for exit signs in accordance with UFC
1212 and UBC Section 1003.2.8.
2.7 SPECIAL TOOLS
A. The Contractor shall provide all
special tools required for operation and maintenance of the
equipment. The tools shall be considered as part of the product and
become the property of the Owner.
PART 3 -
EXECUTION
3.1 GENERAL
A. Install materials and equipment in a
workmanlike manner utilizing craftsmen skilled in the particular
trade. Provide work, which has a neat and finished appearance.
Carry out work in accordance with NECA Standard of Installation
unless otherwise specified.
B. Coordinate electrical work with the
Resident Project Representative and work of all other trades to avoid
conflicts, errors, delays, and unnecessary interference with
operation of the utilities to surrounding residences and businesses
during all phases of construction.
3.2 PROTECTION DURING CONSTRUCTION
A. Throughout this Contract, provide
protection for materials and equipment against loss or damage in
accordance with provisions elsewhere in these Contract Documents.
Throughout this Contract, follow manufacturers' recommendations for
storage. Protect everything from the effects of weather. Prior to
installation, store items in clean, dry, indoor locations. Store in
clean, dry, indoor, heated locations items subject to corrosion under
damp conditions, and items containing electrical insulation, such as
transformers, conductors, motors, and controls. Provide temporary
heating, sufficient to prevent condensation, in transformers,
switchgear, switchboards, motors, and motor control centers, which do
not have space heaters.
B. Following installation, protect
materials and equipment from corrosion, physical damage, and the
effects of moisture on insulation. When equipment intended for indoor
installation is installed at the Contractor's convenience in areas
where it is subject to dampness, moisture, dirt, or other adverse
atmosphere until completion of construction, ensure that adequate
protection from these atmospheres is provided that is
acceptable to the Resident Project Representative. Cap
conduit runs during construction with manufactured seals.
Keep openings in boxes or equipment closed during construction.
Energize all space heaters furnished with equipment.
3.3 SHIPMENT, STORAGE AND
PROTECTION OF EQUIPMENT
A. All indoor electrical panels,
switchgear, MCCs, switchboards, control equipment, etc. shall be
shipped in sealed dust- and moisture-proof plastic sheet enclosures.
The equipment shall be stored in a weatherproof building until
installed, and the sealed shipping enclosure shall be maintained at
all times. The equipment shall always be protected with plastic
sheet covers until all construction and installation work is complete
within the area. This protection shall prevent dust, paint spray,
water, etc. from entering the equipment or causing damage to the
components or finished surfaces.
B. Condensation shall be prevented at
all times. Electrical equipment provided with space heaters shall
have the space heater power supply wiring extended to the outside of
the equipment protective covering. Space heater power shall be
energized from a temporary power source during storage and
installation until the permanent source of space heater power is
connected and energized. This temporary power source shall be from
the Contractor's temporary power system.
C. All exterior surfaces that are
damaged, scratched, etc. shall be repaired and painted with matching
paint as supplied by the manufacturer. The touch-up paint
application shall not be obvious.
3.4
MATERIAL AND EQUIPMENT INSTALLATION
A. Follow manufacturers'
installation instructions explicitly, unless otherwise
indicated.
Wherever any conflict arises between
the manufacturers' instructions, codes and regulations, and these
Contract Documents, follow Resident Project Representative's
decision. Keep copy of manufacturers' installation instructions on
the jobsite available for review at all times.
B. Use appropriate conduit and
conductor entry fittings with enclosures, which maintain the
specified enclosure environmental capability after proper
installation.
C. Motor Installation
1. The Contractor shall verify all
actual motor full-load and locked-rotor current ratings. The minimum
necessary equipment, wire, cable and conduit sizes are shown on the
Contract Documents. If the Contractor furnishes equipment with
different ratings, the Contractor shall determine the actual current
rating of each motor, and furnish the appropriate motor branch
circuit conductor size, the appropriate motor branch circuit
overcurrent protective devices (circuit breaker or motor
short-circuit protector) size, the appropriate motor
branch circuit overcurrent protection setting, the appropriate
motor branch circuit running overload protection, and the appropriate
motor starter size. Affected conduits shall be increased in size as
necessary.
2. The motor branch circuit conductors
shall have a current carrying capacity of not less than 125 percent
of the actual full-load current rating of the motor. The size of the
motor branch circuit conductors shall be such that the voltage drop
from the motor branch circuit overcurrent protective device (breaker
or motor short- circuit protector) to the motor shall not be greater
than two percent when the motor is running at full-load and rated
voltage.
3. The motor branch circuit overcurrent
protective device (circuit breaker or motor short-circuit protector)
shall not operate in less than 30 seconds on the
locked-rotor current of the motor. This device is intended to
protect the motor, motor control device, and branch circuit
conductors against overcurrent due to short-circuit or ground faults.
The motor control circuits shall have the type of overcurrent
protection indicated on the Contract Documents.
4. The motor branch circuit running
overload protection devices shall operate in 20 seconds or less at
motor locked-rotor current to protect the motor from damage under
stalled rotor conditions. The motor branch circuit running overload
protection devices shall be rated or selected to trip the motor at no
more than
125 percent of the motor full-load
current rating for motors marked to have a
temperature rise not over 40°C or a
service factor not less than 1.15. The motor branch circuit running
overload protection devices shall be rated or selected to trip at no
more than 115 percent of the motor full-load current for all other
motors.
5. The motor starter size shall be
coordinated with the current rating and horsepower size of the
installed motor per NEMA standards.
D.
Equipment Installation
1. All equipment shall be anchored
to supporting members by bolts or other connections to
accommodate all operating forces and all forces determined by the
design requirements of the UBC for Occupancy Category I,
Essential Services, in Seismic Zone 4. Equipment shall be secured in
accordance with the manufacturer's recommendations. Embedded
channel shall be installed to anchor enclosures as shown on the
Contract Documents. The Contractor shall submit structural
calculations for seismic restraint.
2. As a minimum, each transformer
mounted on a floor or concrete pad, floor-mounted switchgear
section, motor control section, variable frequency drive section,
control panel or other similar equipment shall have at least one
½-inch stainless steel concrete anchor installed in each corner.
Equipment shall be installed level and aligned in place. Voids shall
be filled with grout. Openings through slabs under equipment shall
be sealed around conduit with grout, synthetic rubber sealing
compound or other approved means. Conduit passing through these
openings shall be sealed with an approved conduit sealant. All
floor-mounted electrical equipment shall be installed on a concrete
pad at least 4 inches in height above the floor, or as noted on the
Contract Documents. Transformers shall be installed with a
containment structure adequate for all oil fill.
Where practicable, and in accordance
with manufacturer's instructions, switchgear, transformers, MCCs,
variable frequency drives, control panels and other similar equipment
shall be secured to channels embedded in or surface- mounted to the
finished floor.
Holes made in existing or new
structures to accommodate electrical installations shall be neatly
formed without rough edges. Repairs to damage caused during
installation shall be made to the satisfaction of the Resident
Project Representative.
E. Torquing of Conductor Terminations:
After installation and before energizing electrical equipment, each
bolted bus and cable connection shall be torqued to the
manufacturer's recommendations. This includes each bolt at each
connection, both factory and field installed, for MCCs, variable
frequency drives, bus ducts, switchgear, and other similar equipment.
3.5 REMOVAL OR RELOCATION OF
MATERIALS AND EQUIPMENT
A. Where existing materials and
equipment are removed or relocated, remove all materials no longer
used such as studs, straps, conduits, and wires. Remove or cut off
concealed or embedded conduit, boxes, or other materials and
equipment to a point at least 3/4-inch below the final finished
surface.
B. Repair affected surfaces to conform
to the type, quality, and finish of the surrounding surface in a neat
and workmanlike manner. Follow any specific instructions given under
Division 9, Finishes. Utilize skilled craftsmen of the trades
involved.
3.6
CUTTING AND PATCHING
A. Lay out work carefully in advance.
Do not cut or notch any structural member or building surface without
specific approval of Engineer. Carefully carry out any cutting,
channeling, chasing, or drilling of floors, walls, partitions,
ceilings, paving, or other surfaces required for the installation,
support, or anchorage of conduit, raceways, or other electrical
materials and equipment. Following such work, restore surfaces
neatly to original condition. Utilize skilled craftsmen of the trades
involved.
3.7 LOAD BALANCE
A. The drawings and specifications
indicate circuiting to electrical loads and distribution equipment.
Balance electrical load between phases as nearly as possible on
switchboards, panelboards, motor control centers, etc.
3.8 PHASING SEQUENCE
A. Coordinate motor phasing checks
with the Resident Project Representative and the Contractor
responsible for the driven equipment. Submit a written report to the
Resident Project Representative for each motor verifying that phasing
has been checked and corrected.
3.9 CLEANING AND TOUCHUP PAINTING
A. Keep the premises free from
accumulation of waste material or rubbish. Upon completion
of work, remove all materials, scraps, and debris from premises and
from interior and exterior of all devices and equipment. Touch up
scratches, scrapes, or chips in interior and exterior surfaces of
devices and equipment with finishes matching as nearly as possible
the type, color, consistency, and type of surface of the original
finish. If extensive damage is done to equipment paint surfaces,
refinish the entire equipment in a manner that provides a finish
equal to or better than the factory finish, that meets the
requirements of the Specifications, and that is acceptable to the
Resident Project Representative.
B. Painting: The Contractor shall
paint conduit, motors, terminal panels, junction boxes, etc. in
accordance with Section 09800 of these Specifications and the
Contract Documents. Red PVC-coated conduit shall not be painted.
Electrical equipment such as
transformers, switchgear, MCCs, control panels, panelboards,
switchboards, etc. shall be painted by the manufacturer
with a corrosion-resistant coating system suitable for a
wastewater pump station environment and shall not be repainted by the
Contractor, except for touch-up paint to repair damage to the factory
finish. Color shall be ANSI No. 61, light gray exterior and white
interior unless otherwise indicated.
Two one-pint spray cans of each coating
used shall be furnished for each freestanding panel assembly.
3.10 HAZARDOUS AREAS
A. Install all materials and equipment
in hazardous areas in a manner acceptable to the regulatory authority
having jurisdiction for the Class, Division, and Group of hazardous
area indicated.
3.11
INSPECTION
A. Allow materials, equipment, and
workmanship to be inspected at any time by the Engineer or
the Resident Project Representative. Correct work, materials, or
equipment not in accordance with these Contract Documents or found to
be deficient or defective in a manner satisfactory to the Resident
Project Representative.
3.12 SERVICE CONTINUITY
A. Maintain continuity of electric
service to all functioning portions of the process or buildings
during hours they are normally in use. Temporary outages will be
permitted during cutover work at such times and places as can be
prearranged with the Resident Project Representative and the
electric utility company providing service to the facility.
All affected residences and business shall be notified at least 24
hours in advance of any outages caused by the construction. Such
outages shall be kept to a minimum number and minimum length of time.
Make no outages without prior written authorization of the Engineer
and notification of the Resident Project Representative. Include
all costs for temporary wiring and overtime work required in
the Contract price. Remove all temporary wiring at the
completion of the work.
3.13 CHECKOUT AND STARTUP
A. During checkout and startup of the
pump station, provide a crew of skilled craftsmen to be available for
checkout and troubleshooting activities as required by the Resident
Project Representative. Since coordination with other crafts and
Contractors will often be required, the craftsmen assigned to
checkout must be available outside normal working hours when
necessary.
3.14 TESTS
A. General: Carry out tests specified
hereinafter and as indicated under individual items of materials and
equipment specified in other sections.
B. Operations: After the electrical
system installation is completed and at such time as the Engineer or
the Resident Project Representative may indicate, conduct an
operating test for approval. Demonstrate that the equipment
operates in accordance with the requirements of these specifications
and drawings. Demonstrate that protective functions are operating
properly and are properly incorporated in control system, circuit
breaker, and motor control center circuitry. Perform the test in
the presence of the Resident Project Representative. Furnish all
instruments and personnel required for the tests.
END OF SECTION
No comments:
Post a Comment